New
Master Descriptive Writing with our RBI One-Month Batch!
Login
Register
More Topics
Home
Questions
Quantitative Aptitude
Time and work
Practice Time and work Questions and Answers
Question Listing
An elephant can do a work as fast as two horses ‘A’ and ‘B’ can do it by working together. If horse ‘A’ alone can complete the work in 38 hours...
X men can complete the piece of work in 35 days and (X + 34) men can complete the same work in 14 days less than that of days taken by X men. Find the valu...
X men can complete the piece of work in 50 days and (X + 51) men can complete the same work in 30 days less than that of days taken by X men. Find the valu...
X men can complete the piece of work in 45 days and (X + 46) men can complete the same work in 23 days less than that of days taken by X men. Find the valu...
X men can complete the piece of work in 32 days and (X + 30) men can complete the same work in 15 days less than that of days taken by X men. Find the valu...
X men can complete the piece of work in 36 days and (X + 35) men can complete the same work in 14 days less than that of days taken by X men. Find the valu...
X men can complete the piece of work in 36 days and (X + 30) men can complete the same work in 15 days less than that of days taken by X men. Find the valu...
A takes 32 days to complete a work while B can complete the same work in 12 days less than A. If C can complete 25% of the work in 12 days, then find the t...
A and B can complete a work together in 20 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed by ...
A and B can complete a work together in 25 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed by ...
A and B can complete a work together in 30 days. If A alone can complete one-third of the work in ‘x’ days and remaining work is completed by B alone i...
A and B can complete a work together in 32 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed by ...
A and B can complete a work together in 36 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed by ...
A and B can complete a work together in 36 days. If A alone can complete one-third of the work in lsquo;xrsquo; days and remaining work is completed by B a...
A and B can complete a work together in 24 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed by ...
A and B can complete a work together in 20 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed by ...
A and B can complete a work together in 18 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed by ...
A and B can complete a work together in 18 days. If A alone can complete one-third of the work in ‘x’ days and remaining work is completed by B...
‘A’ can do a piece of work in 12 days. ‘B’ can do 70% of the same work in 30 days. If they work together for the entire time and ge...
‘A’ can do a piece of work in 8 days. ‘B’ can do 40% of the same work in 16 days. If they work together for the entire time and get paid Rs.1500, t...
‘A’ can do a piece of work in 10 days. ‘B’ can do 80% of the same work in 12 days. If they work together for the entire time and get paid Rs.1200, ...
‘A’ can do a piece of work in 15 days. ‘B’ can do 60% of the same work in 20 days. If they work together for the entire time and get paid Rs.1450, ...
‘A’ can do a piece of work in 20 days. ‘B’ can do 80% of the same work in 30 days. If they work together for the entire time and get paid Rs.1610, ...
‘A’ can do a piece of work in 10 days. ‘B’ can do 80% of the same work in 20 days. If they work together for the entire time and get paid Rs.1400, ...
‘A’ can do a piece of work in 12 days. ‘B’ can do 60% of the same work in 18 days. If they work together for the entire time and get paid Rs.1540, ...
‘A’ can do a piece of work in 15 days. ‘B’ can do 80% of the same work in 20 days. If they work together for the entire time and get paid Rs.1408, ...
‘A’ can do a piece of work in 10 days. ‘B’ can do 70% of the same work in 20 days. If they work together for the entire time and get paid Rs.1080, ...
‘A’ can do a piece of work in 15 days. ‘B’ can do 70% of the same work in 20 days. If they work together for the entire time and ge...
‘A’ alone can complete a work in 40 days while ‘A’ and ‘B’ together can complete the same work in 20 days. How much per...
‘A’ alone can complete a work in 50 days while ‘A’ and ‘B’ together can complete the same work in 20 days. How much percentage of the work, ‘...
‘A’ alone can complete a work in 15 days while ‘A’ and ‘B’ together can complete the same work in 10 days. How much percentage of the work, ‘...
Karan, Arjun and Krunal alone can complete a work in 30, 45 and 36 days respectively. All of them started working together but after 3 days from start Kara...
Karan, Arjun and Krunal alone can complete a work in 40, 60 and 48 days respectively. All of them started working together but after 3 days from start Kara...
Karan, Arjun and Krunal alone can complete a work in 50, 75 and 60 days respectively. All of them started working together but after 9 days from start Kara...
Karan, Arjun and Krunal alone can complete a work in 35, 70 and 60 days respectively. All of them started working together but after 3 days from start Kara...
A, B and C alone can complete a work in 12, 24 and 20 days respectively. All of them started working together but after 2 days from start A left the job an...
A, B and C alone can complete a work in 24, 48 and 32 days respectively. All of them started working together but after 2 days from start A left the job an...
A, B and C alone can complete a work in 18, 32 and 24 days respectively. All of them started working together but after 3 days from start A left the job an...
A, B and C alone can complete a work in 20, 30 and 25 days respectively. All of them started working together but after 4 days from start A left the job an...
A, B and C alone can complete a work in 30, 60 and 45 days respectively. All of them started working together but after 3 days from start A left the job an...
Page 10 of 13
Previous
1
2
...
7
8
9
10
11
12
13
Next
Last
More Topics
×
Addition & subtraction Questions
Age Questions
Algebra Questions
Alligation Questions
Approximation Questions
Arithmetic Progression Questions
Average Questions
Bar graph Questions
Binomial Equation Questions
Boats and streams Questions
Calculation based Questions
Caselet DI Questions
Circle Questions
Clock and Calendar Questions
Compound Interest Questions
Coordinate Geometry Questions
Cube & cube roots Questions
Data Sufficiency Questions
Databased Questions
Databased Partnership Questions
Databased Profit Loss and discount Questions
Databased Ratio Questions
Databased Time and Work Questions
DI Questions
Di Bar Graph Questions
DI Line Graph Questions
DI Pie Chart Questions
DI PIE Chart and Ratio Table Questions
DI Tables Questions
Di With Missing Numbers Questions
Differential Equation Questions
Discount Questions
Divisibility rules Questions
Equality and Inequality Questions
Equations Questions
Fractions Questions
Geometry Questions
HCF and LCM Questions
Height and Distance Questions
Income and Expenditure Questions
Integration Questions
Limits and Continuity Questions
Line graph Questions
Linear Equation Questions
Lines and Angles Questions
Maxima and Minima Questions
Mensuration Questions
Missing DI Questions
Mixture Questions
No. System Questions
Partnership Questions
Percentage Questions
Permutation and combination Questions
Pipes and cisterns Questions
Polygon Questions
Probability Questions
Profit and loss Questions
Quadratic equation Questions
Quadrilateral Questions
Quant Miscellaneous Questions
Quantity Inequality Questions
Radar graph Questions
Ratio Questions
Ratio and proportion Questions
SI and CI databased Questions
Simple and compound interest Questions
Simplification Questions
Square & square root Questions
Surds and indices Questions
Time Questions
Time and distance Questions
Trains Questions
Triangle Questions
Trigonometry Questions
Uniatry Method Questions
Weekly Quiz Quant Questions
Wrong Series Questions
Today's Class
There is no live class for today.
×
I Pledged to:
callback wala button
×
Please Enter Details
Please enter Name
We'll never share your email with anyone else.
Please enter Correct Mobile Number
We'll never share your email with anyone else.
Request a Call Back
Thank You
Update Address
Please enter complete address
Please enter pincode
Please enter State
Select State
Please enter City
Add Address
Download the app
×
X
×