Question
16 man can make a wall in 3 days. How many men required
to complete the same work in 8 days ?Solution
Given, M1 = 16, D1 = 3, M2 = ? and D2 = 8 From M1D1 = M2D2 β 16 x 3 = M2 x 8 β M2 = (16 x 3)/8 β΄ M2 = 6
Which approach best reduces customer churn?
Priority Sector Lending (PSL) guidelines are issued by:
Panasonic Smart TVs come with a 1-800 number for customers to call and receive help setting up their new machine. This is an example of:
Cost incurred for each ad click is:
According to one of the world's largest publishers, it was unprepared for recent increases in the demand for books about security. To prepare for the sh...
A bank launches a youth-focused savings account with cashback on online gaming and streaming subscriptions. This is an example of:
Which promotion tool is unpaid?
_________ believes that the consumers will favour those products that offer the best quality, performance and features and therefore the organisation s...
Demand is an economic principle referring to a consumer's desire to purchase goods and services:
A local micro-brewery uses a nearby stream to power a water-mill to generate electricity to heat their hops and yeast during the beer fermentation proce...