Question
"'Mahesh' is 40% less efficient than 'Neeraj.' 'Neeraj'
takes 30 days fewer than 'Mahesh' to finish the same work. Find the time taken by 'Neeraj' to finish the work while working at 80% of his efficiency."Solution
ATQ, Let the efficiency of 'Neeraj' be '10n' units/day So, efficiency of 'Mahesh' = 10n × 0.6 = '6n' units/day So, ratio of efficiency of time taken by 'Mahesh' and 'Neeraj' = 10n:6n = 5:3 Let time taken by 'Mahesh' and 'Neeraj' to finish some work be '5m' day and '3m' days. So, 5m - 3m = 30 So, 2m = 30 So, m = 15 And time taken by Neeraj to finish the work = 3 × 15 = 45 days So, required time = 45 ÷ 0.8 = 56.25 days
- In which state is the Tobacco Board's main office located?
- Who is known in India as the 'Bharat Kumar'?
Which gas is most abundant in the Earth’s atmosphere?
- Which European nation appointed Duro Macut as Prime Minister in April 2025?
Match the following crops with their highest-producing states in India:
Which of the following statements about the export ban on non-basmati white rice is correct?
1. The ban was imposed in July 2023 to control domes...
What is the currency of Japan?Â
- Which of the following statements is/are true?
(I) India, Pakistan, and China followed similar development planning models.
(II) India undertook stru... Who has been appointed as the brand ambassador of Fit India Movement in February 2024?
Which of the following pairs is correctly matched?