Question
"'Mahesh' is 40% less efficient than 'Neeraj.' 'Neeraj' takes 30 days fewer than 'Mahesh' to finish the same work. Find the time taken by 'Neeraj' to finish the work while working at 80% of his efficiency."
More Time and work Questions
- 'A' alone can do some work in 10 days. 'B' is 25% more efficient than 'A'. 'A' worked alone for 5 days and left. How much time (in days) does 'B' need to f...
- An investment at 18% simple interest for 2 years gives Rs. 1,800 as interest. What would be the interest if the same sum is invested at 12% for 4 years?
- ‘A’ is 25% more efficient than ‘B’. ‘A’ and ‘B’ work together for 5 days after which ‘A’ is replaced by ‘C’. ‘B’ and ‘C’ together take 5 more days to finis...
- Ayaan and Kabir started working together on a task. Ayaan does 4 units per day and Kabir can finish the full task in 25 days alone. The total work is 100 u...
- Akhil and Nikhil together can complete a work in 10 days while Nikhil alone takes 15 days to complete 30% of the work. If the efficiency of Sachin is 25% m...
- 45 people can repair a road in 10 days working 6 hours a day. In how many days can 30 people working 6 hours a day complete the same work?
- Arjun and Karan can do a work separately in 20 days and 50 days respectively. Arjun started the work and was later joined by Karan. When should Karan join ...
- A does 2/5 of a work in 9 days. Then B joined him and they together completed the remaining work in 6 days. B alone can finish the whole work in
- 24 male working 12 hours per day can finish a piece of work in 30 days, while 36 female working 8 hours per day can finish the same work in 60 days. Which...
- ‘D’ and ‘E’ together finish a task in 20 days. If ‘D’ is 70% more efficient than ‘E’, how many days will ‘E’ take to complete the task alone?