    Question

    Ashish and Anil can do a piece of work in 18 days and 24

    days respectively. Ashish completed 25% of the work. Find the time taken by Anil to complete the remaining work.
    A 15 days Correct Answer Incorrect Answer
    B 18 days Correct Answer Incorrect Answer
    C 11 days Correct Answer Incorrect Answer
    D 7 days Correct Answer Incorrect Answer

    Solution

    Let the total work be (LCM of 18 and 24) = 72 units Efficiency of Anil = 72/24 = 3 units/day Remaining work = 72 x 0.75 = 54 units Time taken by Anil to complete the remaining work = 54/3 = 18 days