Question
Ashish and Anil can do a piece of work in 18 days and 24
days respectively. Ashish completed 25% of the work. Find the time taken by Anil to complete the remaining work.Solution
Let the total work be (LCM of 18 and 24) = 72 units Efficiency of Anil = 72/24 = 3 units/day Remaining work = 72 x 0.75 = 54 units Time taken by Anil to complete the remaining work = 54/3 = 18 days
Sum of three positive numbers is 126. If the ratio of the first and second number is 4:5, respectively while difference between the first and third num...
Three natural numbers X,Y,Z are pairwise co-prime and satisfy the following conditions, the least common multiple (LCM) of X and ...
Find the sum of all natural numbers less than 500 which are divisible by 7.
Sahil can make a toy in 3 hrs, 25 minutes and 13 seconds. How much time he will take to make 8 such toys?
Find the smallest 4-digit number which is exactly divisible by 6, 9 and 15.
- Calculate the largest 5-digit number which is divisible by β64β
What is the average of all the prime numbers which are less than 35?
'M' is the largest three-digit number that leaves 3 as a remainder when divided by 9, 12 and 5, Find the sum of digits of 'M'.
The square of the sum of two numbers is 784. The sum of squares of these numbers is 520. Find their product.