Ashish and Anil can do a piece of work in 18 days and 24
days respectively. Ashish completed 25% of the work. Find the time taken by Anil to complete the remaining work.Solution
Let the total work be (LCM of 18 and 24) = 72 units Efficiency of Anil = 72/24 = 3 units/day Remaining work = 72 x 0.75 = 54 units Time taken by Anil to complete the remaining work = 54/3 = 18 days
Difference between the number of females of tribe Raba and Dimasa together is approximately what percent of the total population of tribe Dimasa?
If the boutique introduces a new product line of Accessories with a cost price of ₹400 and a selling price of ₹600, and they sell 200 units in the n...
Number of male employees in HR department was how much percent more/less than the number of female employees in Marketing department?
How many students appeared in exam X or in exam Z?
If a mixture contains milk and water in the ratio of 4: 1. If 20% of mixture is taken out and same amount of milk and water are added into mixture, then...
What is the difference between the number of students participated from school C and the number of girls participated from school A and B together?
How many students appeared in two exams only?
Find the difference between the number of males and number of females of tribe Raba.
Find ratio between total employees in HR and Management.
Find the ratio of initial quantity of vessel A and the left quantity of water in vessel C after removing 40%.