Question
Ashish and Anil can do a piece of work in 18 days and 24
days respectively. Ashish completed 25% of the work. Find the time taken by Anil to complete the remaining work.Solution
Let the total work be (LCM of 18 and 24) = 72 units Efficiency of Anil = 72/24 = 3 units/day Remaining work = 72 x 0.75 = 54 units Time taken by Anil to complete the remaining work = 54/3 = 18 days
In India, which of the following regulatory mechanisms was NOT in existence to enforce regulation of the industrial sector?
Which Indian air exercise conducted in 2024 focuses on improving interoperability with Friendly Foreign Countries?
Which Indian bank has the lowest net NPAs as of FY24?
Who were the recipients of the Indira Gandhi Peace Prize for 2023, and for what contributions?Â
How many vehicle categories are now eligible for incentives under Maharashtra's new EV Policy 2025?
According to the information provided by the Labour Bureau,the year-on-year inflation for the month stood at _____ compared to 6.16 per cent for the pre...
The 'Centre of Jain Manuscriptology' established at Gujarat University is funded by the Ministry of Minority Affairs with how much budget?
The Green Revolution term was first used by which person?
What is the significance of the new plant species Emblica chakrabartyi discovered in Kerala?
Recently ‘e-stamp facility’ has been launched by which state/UT?