Question
Ashish and Anil can do a piece of work in 18 days and 24
days respectively. Ashish completed 25% of the work. Find the time taken by Anil to complete the remaining work.Solution
Let the total work be (LCM of 18 and 24) = 72 units Efficiency of Anil = 72/24 = 3 units/day Remaining work = 72 x 0.75 = 54 units Time taken by Anil to complete the remaining work = 54/3 = 18 days
How many such numbers are there which is preceded by alphabets and followed by symbols?
- How many alphabets are immediately preceded by a number?
The term ‘toast’ is related to _______________.
What will be the next term in the series?
I, V, X, L, C, D, ?
What will come in place of question mark (?) in the following series?
DLNÂ Â Â Â Â Â Â CKOÂ Â Â Â Â Â BJQÂ Â Â Â Â Â Â ? Â Â Â Â Â ZHX
- Select the combination of letters that when placed sequentially in the blanks of the given letter series will complete the series.
I _ P _ O V _ D ... In the given arrangement, how many such numbers are there which immediately followed by a letter?
How many vowels are there in all the words if the last alphabet in each alphabet is replaced by the succeeding letter?
Select the combination of letters that when sequentially placed in the blanks of the given letter series will complete the series.
D E D D E _...
Select the combination of letters that when sequentially placed in the blanks of the given letter series will complete the series.