      Question

      Efficiency of a man is 25% more than that of a woman. (2n + 4) men working 8 hours a day can complete a task in 18 days, whereas (3n - 2) women working 6 hours a day can complete the same task in 24 days. Find the time taken by (n - 6) men and (n - 8) women working 9 hours a day to complete the task.

      A 24 days Correct Answer Incorrect Answer
      B 30 days Correct Answer Incorrect Answer
      C 32 days Correct Answer Incorrect Answer
      D 36 days Correct Answer Incorrect Answer
      E 40 days Correct Answer Incorrect Answer

      Solution

      Let the efficiency of a woman be '4e' units/day. Then, efficiency of a man = (5/4) Γ— 4e = '5e' units/day. ATQ; (2n + 4) Γ— 8 Γ— 18 Γ— 5e = (3n - 2) Γ— 6 Γ— 24 Γ— 4e Or, 1440n + 2880 = 1728n - 576 Or, 2880 + 576 = 1728n - 1440n Or, 3456 = 288n Or, 'n' = 12 Total work = (2n + 4) Γ— 8 Γ— 18 Γ— 5e = (28) Γ— 8 Γ— 18 Γ— 5e = '20160e' units So, required number of days to complete the work = 20160e Γ· [(6 Γ— 5e + 4 Γ— 4e) Γ— 9] = 20160e Γ· (46e Γ— 9) = 20160e Γ· 414e = 40 days

      Practice Next
      More Time and work Questions

      Relevant for Exams:

      ask-question