Question
45 engineers working 5 hours a day take 15 days to complete a project. How many engineers working for 4 hours a day are needed to complete three times the given project in 20 days if they work at 20% higher efficiency?
More Time and work Questions
- ‘A’ and ‘B’ can do a piece of work in 10 days and 15 days, respectively. They started working together but ‘A’ left after 3 days. Find the time taken by ‘B...
- There is enough food in a camp to last for 30 days if each of the 100 soldiers present at the camp eat 3 times a day. After 20 days, 50 soldiers left the c...
- Gagan can do a piece of work in 14 days. Magan is 40% more efficient than Gagan. How many days will Magan and Gagan together complete the work?
- A certain number of students can complete the assignment together in 12 days. All of them started the assignment together, but 20 students left the assignm...
- 'Ravi', 'Sohan', and 'Karan' can individually finish a task in 45, 30, and 60 days, respectively. Sohan and Karan work together for ‘x’ days and then leave...
- A and B individually can complete the work in 32 days and 48 days respectively. If the time taken by C alone to complete the work is 1.25 times the time ta...
- A team leader can do a job as fast as three members of the team working together. If one of the member can do the job in 5 hrs, the second one takes 10 hrs...
- The time taken by ‘X’, ‘Y’ and ‘Z’ to complete a task is ‘6n’ days, ‘9n’ days and ‘12n’ days, respectively. What is the ratio of their efficiencies?
- ‘M’ is 60% more efficient than ‘N’. ‘N’ started the work alone and worked for 16 days and after that ‘N’ is replaced by ‘M’. If the total work is completed...
- What is B’s share (in ₹)? I: A and B together can complete a piece of work in 12 days. B and C together can complete the same work in 16 days. A and C tog...