Question
45 engineers working 5 hours a day take 15 days to complete
a project. How many engineers working for 4 hours a day are needed to complete three times the given project in 20 days if they work at 20% higher efficiency?Solution
ATQ,
Let the total work be 'W' units and the efficiency of each engineer be 'E' units/hour.
Let the number of engineers required be 'M'.
ATQ:
Which company won four gold awards at the Olive Crown Awards 2025?
The objective of Bima Vahak continues to be a women-centric, dedicated distribution channel that will ensure accessibility and availability of insurance...
- Which dynasty founded the Vijayanagar Empire?
Who authored the book *‘Divorce and Democracy: A History of Personal Law in Post-Independence India’*?Â
From which site was India’s first satellite Aryabhata launched?
Who was elected as the President of the 68th General Conference of the International Atomic Energy Agency (IAEA) in September 2024?
Who, in a historic achievement, has become the first female medical officer in the Indian Army to be stationed at Siachen, the highest battlefield in th...
- Who holds the distinction of being the first judge against whom impeachment proceedings were initiated in independent India?
Who is the chairperson of the working group for the revision of WPI base year and transition to PPI?
"Exercise Sea Dragon 2026" is a US-led multinational exercise. In which region was it conducted in March 2026?