Question

    'X', 'Y', and 'Z' can complete a job individually in 20

    days, 30 days, and 24 days respectively. 'Y' and 'Z' begin the task together. After 6 days, 'Z' leaves and 'X' joins 'Y' to finish the job. Determine the total number of days required to complete the task.
    A 27.2 Correct Answer Incorrect Answer
    B 12.6 Correct Answer Incorrect Answer
    C 33.5 Correct Answer Incorrect Answer
    D 10.5 Correct Answer Incorrect Answer
    E None of these Correct Answer Incorrect Answer

    Solution

    ATQ,

    Let the total work be 120 units (LCM of 20, 30, and 24)

    Efficiency of 'X' = 120 ÷ 20 = 6 units/day

    Efficiency of 'Y' = 120 ÷ 30 = 4 units/day

    Efficiency of 'Z' = 120 ÷ 24 = 5 units/day

    Let the total time taken be T days.

    So, (4 + 5) × 6 + (6 + 4) × (T − 6) = 120

    ⇒ 54 + 10(T − 6) = 120

    ⇒ 54 + 10T − 60 = 120

    ⇒ 10T = 126

    ⇒ T = 12.6 days

    Practice Next

    Relevant for Exams: