Question
A can complete a work in 9 days , and B can complete it in 18 days . They work together with C and complete the work in 3 days . In how many days can C alone complete the work?
More Time and work Questions
- A can complete a work in 9 days , and B can complete it in 18 days . They work together with C and complete the work in 3 days . In how many days can C...
- Lucas, Maya, and Riley can build a wall in 5, 10, and 15 days respectively. If they start the job together and Lucas leaves 3 days before the job is done, ...
- Rohit and Usha can complete a task individually in 24 days and 60 days, respectively. When they work together along with Vipul, the same task is finished i...
- A certain amount earns Rs. 2,400 as simple interest in 4 years at 12% per annum. If the same amount is invested at 8% per annum for 2 years, what will be t...
- 'A' and 'B' together can do a piece of work in 12 days while 'B' and 'C' together can do the same work in 18 days. 'A' started the work alone and worked on...
- Rajesh and Bhupesh can complete a piece of work in 20 days and Bhupesh alone in 25 days. In how many days can Rajesh alone complete the work?
- Virat can do a piece of work in 26 days and Sachin can do the same work in 39 days. If Virat works for 5 days and got Rs. 3000, and the remaining work will...
- Riya can do a piece of work in 30 days, and Mehul can do it in 45 days. Find the number of days Kabir will take to complete the job if he is 20% more effic...
- A group of 3 men and 5 women can finish a task in 12 days, while another group of 5 men and 3 women can complete the same task in 9 days. If one man and on...
- Three men and 4 women can do a piece of work in 7 days, whereas 2 men and I woman can do it in 14 days. Seven women will complete the same work in:
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt