    Question

    A can complete a work in┬а 9 days , and B can complete

    it in┬а 18 days . They work together with C and complete the work in┬а 3 days . In how many days can┬а C alone ┬аcomplete the work?
    A 10 days Correct Answer Incorrect Answer
    B 12 days Correct Answer Incorrect Answer
    C 18 days Correct Answer Incorrect Answer
    D 21 days Correct Answer Incorrect Answer
    E None of these Correct Answer Incorrect Answer

    Solution

    Assume total work = LCM(9, 18) = 18 units AтАЩs rate = 18/9 = 2 units/day BтАЩs rate = 18/18 = 1 unit/day Let CтАЩs rate = x units/day Total rate = (2 + 1 + x) units/day = (3 + x) They finish in 3 days: (3 + x) ├Ч 3 = 18 9 + 3x = 18 3x = 9 тЖТ x = 3 units/day Time for C alone = 18 / 3 = 6 days