πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      105 people could complete a work in 36 days. But after

      they worked together for 7 days their employer wanted the work should be completed in a total of 28 days. How many more workers need to be employed to meet the deadline?
      A 36 Correct Answer Incorrect Answer
      B 40 Correct Answer Incorrect Answer
      C 28 Correct Answer Incorrect Answer
      D 46 Correct Answer Incorrect Answer

      Solution

      Let the efficiency of each worker be X. Now, the total work = 105 Γ— X x 36. Let Y number of workers need to be employed to get the work done in 28 days. Work done in 7 days = 105 Γ— X x 7 = 735X Remaining days = 28-7 =21 days Work done in 21 days = (105 + Y) x X Γ— 21 According to the concept, 105 x X x 36 = 735X+ (105 + Y) Γ— X Γ— 21 105 x 36 = 735 + (105 + Y) x 21 3780=735 + 2205 + 21Y 21Y=840 Y = 840/21 Y = 40 Β  40 more workers need to be employed to meet the deadline.

      Practice Next

      Relevant for Exams:

      ask-question