Question
105 people could complete a work in 36 days. But after
they worked together for 7 days their employer wanted the work should be completed in a total of 28 days. How many more workers need to be employed to meet the deadline?Solution
Let the efficiency of each worker be X. Now, the total work = 105 Ă— X x 36. Let Y number of workers need to be employed to get the work done in 28 days. Work done in 7 days = 105 Ă— X x 7 = 735X Remaining days = 28-7 =21 days Work done in 21 days = (105 + Y) x X Ă— 21 According to the concept, 105 x X x 36 = 735X+ (105 + Y) Ă— X Ă— 21 105 x 36 = 735 + (105 + Y) x 21 3780=735 + 2205 + 21Y 21Y=840 Y = 840/21 Y = 40 Â 40 more workers need to be employed to meet the deadline.
The soils of very cold climates which are defined as containing permafrost within two meters of the soil surface belongs to the order
Which of the following fatty acid is majorly present in Coccus nucifera?
Which of the following is non-edible oilseed?
In rust cycle, wheat is infected by which of the following spores?
ICAR – Central Institute of Agriculture Engineering is located at
Inflorescence of soyabean is
Which plant is used for control of blood pressure?
Panama wilt in banana is caused by
The spread of numerical value from the mean value is called?
Gossypol toxin is produced in