Question
A man can complete a work in 12 days. He worked for 5 days and then left. If the remaining work is completed by another man who can complete it in 18 days, how long will it take for the second man to finish the work?
More Quant Miscellaneous Questions
- The angle of elevation of the top of a building from a point on the ground is 60°. After walking 20 meters towards the building, the angle of elevation bec...
- If f(x) is periodic of period T, then:
- Question 3
- The angle between the planes x − y + z = 1 and 2x + y − 3z = 5 is:
- At 9:30 a.m., the length of a pole’s shadow is equal to its height. What is the sun’s altitude at this time?
- The speed ratio of train A to train B is 3:2, and both trains are of equal length. Train A takes x seconds to cross train B when they are moving in the sam...
- A 60-liter solution contains 30% alcohol. How much pure alcohol must be added to make the solution 50% alcohol?
- A person’s salary rose by 50%. In reaction, he decided to raise his spending by 30%. If he used to save 20% of his income earlier, what is the percentage g...
- 9 5 6 10.5 23 ? 183
- In how many ways can 4 distinct books be distributed into 2 identical boxes such that no box is empty?
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt