Question
A man can complete a work in 12 days. He worked for 5 days and then left. If the remaining work is completed by another man who can complete it in 18 days, how long will it take for the second man to finish the work?
More Quant Miscellaneous Questions
- The following table shows the number of students enrolled in different courses at a university: What is the percentage of students enrolled in Mathematic...
- A container holds a mixture of juice and water in the ratio of 5:2. When 6 liters of juice are added to the mixture, the ratio of juice to water changes to...
- The pie chart below represents the degree distribution of employees across five different offices, with a total of 4500 employees in all five offices combi...
- Calculate the total percentage increase in employees from 2019 to 2023 for the entire company.
- If a line has direction ratios 2, – 1, – 2, determine its direction cosines.
- If x² – 6x + m > 0 for all real x, find m.
- Find the value of x in 5 (5x – 6) = 25 (3x – 3)
- Six years from now, the ratio of Krishna's age to his age two years ago is 3:2. Currently, Gaurav is 14 years older than Krishna. If Juju's current age is ...
- The income of ‘A’ increases by 25% every year. If the present income of ‘A’ is Rs. 28125 and his expenditure 2 years ago from now was Rs. 12000, then find ...
- Determine the area of an equilateral triangular field having perimeter of 42m.
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt