📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!


    Question

    Ratio of the work done by P, Q and R in one day is 7:4:9

    respectively. They all together can complete the work in 44 days. Q and R worked on it for 30 days. In how many days P will complete the remaining work.
    A 70 days Correct Answer Incorrect Answer
    B 65 days Correct Answer Incorrect Answer
    C 88 days Correct Answer Incorrect Answer
    D 78 days Correct Answer Incorrect Answer

    Solution

    Let total amount work be = 44 x 20 = 880 units Amount of work done by Q and R in 30 days = 30 x 13 = 390 units Amount of work left = 880 – 390 = 490 Required time = 490/7 = 70 days

    Practice Next
    ask-question

    Not sure which exam is best for you Talk to our expert

    Get My Free Call