Question
Ratio of the work done by P, Q and R in one day is 7:4:9 respectively. They all together can complete the work in 44 days. Q and R worked on it for 30 days. In how many days P will complete the remaining work.
More Time and work Questions
- A person can make 48 flower pots in an hour. Working for 3 hours daily, he has total 660 flower pots that to be made in 4 days time. To accomplish this wor...
- Rahul, Sameer, and Dinesh can complete a task in 24 days, 36 days, and 18 days, respectively. They started working together, but Rahul left after 3 days. H...
- ‘M’ and ‘N’ together can do a piece of work in 50 days. If ‘M’ is 50% more efficient than ‘N’, how long will ‘N’ take to do the work alone?
- 30 typists working 7 hours per day can complete a typing job in 15 days. ____ typists working _____ hours per day can complete (2/3)rd part of the work in ...
- Anupam can do a piece of work in 36 days and Rajveer can do it in 15 days. Diksha can do the same work in (17/18) times the number of days required by both...
- 'A' alone can do some work in 24 days, 'B' alone can do the same work in 48 days. If they work on alternate days, starting with 'B', then the work will be ...
- P alone can finish a piece of work ‘M’ in 8 days while Q takes 4 days to finish it alone. P, Q and R working together can finish the work &lsqu...
- Team A can built a project in 4 hours less than the time taken by Team B to built the same project. The ratio of the strength of Team A to that of Team B ...
- Time taken by 'X' and 'Y' to complete a work alone is 72 days and 120 days respectively. Find the time taken by 'X' and 'Y' together to complete 25% of the...
- Three men A, B, and C working together dig 648 m deep in six days. C digs as many meters more than B. B digs as many meters more than A. Then how much digg...