Question
Ratio of the work done by P, Q and R in one day is 7:4:9
respectively. They all together can complete the work in 44 days. Q and R worked on it for 30 days. In how many days P will complete the remaining work.Solution
Let total amount work be = 44 x 20 = 880 units Amount of work done by Q and R in 30 days = 30 x 13 = 390 units Amount of work left = 880 – 390 = 490 Required time = 490/7 = 70 days
Directions: In each question below, four words printed in bold type are given. These are numbered (A), (B), (C) and (D). One these words printed in bol...
Choose the correctly spelt word.
In each group, one word is correctly spelt. Find the correct word.
India is one of their favourite destinations for this trail .
- Select the INCORRECTLY spelt word:
In each of the questions below, a sentence is given with four words highlighted in bold in the sentence. Among these bold words, one may be wrongly spe...
- In each of the questions below, a sentence is given with four words highlighted in bold in the sentence. Among these bold words one may be wrongly spelt. T...
The more money the governments pored into it, the harder it was to walk away.
...(a) Tariff (b) Tarriff
(c) Tarif (d) Tarrif
- In each of the questions below, a sentence is given with four words highlighted in bold in the sentence. Among these bold words, one may be wrongly spelt. ...