Question
40 men take 15 days to finish some work. If the work is
to be finished in 8 days, then how many additional men should be hired?Solution
Let the total work be 'w' units and efficiency of each man be 'e' units/day Let number of men required to finish the work in 8 days be 'm'. ATQ; W/(40 x 15 x e) =Â W/(8 x e x m) Â m = 75 So, 75 - 40 = 35 more men should be hired.
Which body serves as the national authority for air pollution control under the Air Prevention and Control of Pollution Act, 1981?
What conditions must be met for the Authority to grant a certificate of registration to an applicant to operate as an insurer under the Insurance Act?
Which ground of judicial review establishes that 'the concerned administrative action should not be more forceful than it requires to be'?
The Act allows withdrawal of consent:
If an assembly was lawful at the beginning but later adopted a common object falling under Section 189(1), what is its legal status?
Section 10 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, deals with which of the fo...
What is the timeframe within which the Tribunal should aim to decide an appeal as per section 23 of the Code on Social Security?
Which of the following correctly characterizes the constitutional status of the State Election Commission?
The PFRDA regulates which of the following_____________
When was Criminal Procedure Code enacted?