Question
40 men take 15 days to finish some work. If the work is to be finished in 8 days, then how many additional men should be hired?
More Time and work Questions
- If Ankit takes four times the time that Ravi takes or five times the time that Sandeep takes to finish a task, and all three working together can complete ...
- G' can complete (3/4) of a job in 24 days, while 'G' and 'H' together can complete the same job in 16 days. Find the time taken by 'H' to complete 25% of ...
- Working individually, 'A' can finish 60% of a task in 18 days, and 'B' takes 15 days longer than 'A' to complete the entire task. However, 'B' and 'C' work...
- 'N' men can complete a work together in 25 days. All of them started the work together, but each day, two men left the work. The total time taken to comple...
- What is B’s share (in ₹)? I: A and B together can complete a piece of work in 12 days. B and C together can complete the same work in 16 days. A and C tog...
- A, B and C can complete a piece of work in 12 days, 18 days and 36 days respectively (working alone). They all start working together. After 2 days, C leav...
- The time taken by ‘A’ to build a wall alone is 50% more than the time taken by him to build it along with ‘B’. ‘B’ will take how much percent more time to ...
- A’ and ‘B’ together can complete a work in 10 days while ‘A’ takes 18 days to complete the same work alone. If ‘C’ is 25% more efficient than ‘B’, then fin...
- Ten men begin to do work. But after some days, four of them left the job. As a result, the job that could have been completed in 40 days is completed in 50...
- Four lights blink at intervals of 18 seconds, 24 seconds, 36 seconds, and 48 seconds respectively. How many times will all the lights blink together in 3 h...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt