📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!


    Question

    X and Y alone can complete a work in 10 and 40 days,

    respectively. 50% of the work is completed by Z in 20t days, and the remaining work is completed by X and Y working together in ‘t’ days. Find the time taken by Y and Z to complete the whole work while working together.
    A 20 days Correct Answer Incorrect Answer
    B 40 days Correct Answer Incorrect Answer
    C 30 days Correct Answer Incorrect Answer
    D 32 days Correct Answer Incorrect Answer

    Solution

    Time taken by X and Y to complete the whole work while working together = (10 × 40)/(10 + 40) = 8 days So, t = 8/2 = 4 (Since, 50% of the work is done by X and Y together) As, time taken by Z to complete 50% of the work = 4 × 20 = 80 days So, time taken by Z to complete the entire work = 80 × 2 = 160 days Therefore, time taken by Y and Z to complete the whole work while working together = (160 × 40)/(160 + 40) = 32 days

    Practice Next

    Relevant for Exams:

    ask-question

    Not sure which exam is best for you Talk to our expert

    Get My Free Call