Question
X and Y alone can complete a work in 10 and 40 days,
respectively. 50% of the work is completed by Z in 20t days, and the remaining work is completed by X and Y working together in ‘t’ days. Find the time taken by Y and Z to complete the whole work while working together.Solution
Time taken by X and Y to complete the whole work while working together = (10 × 40)/(10 + 40) = 8 days So, t = 8/2 = 4 (Since, 50% of the work is done by X and Y together) As, time taken by Z to complete 50% of the work = 4 × 20 = 80 days So, time taken by Z to complete the entire work = 80 × 2 = 160 days Therefore, time taken by Y and Z to complete the whole work while working together = (160 × 40)/(160 + 40) = 32 days
Priya has joined Twitter and has 8 friends and each of these friends has 12 friends. Later, it is found that at least two of her friends know each othe...
- What is to be subtracted from (13/20) so that the result is (7/25)?
When a number is increased by 60% then the number obtained is 56 less than thrice the original number. Find the original number.
The sum of the exponents of the prime factors in the prime factorization of 225 is
Mohit purchased some toffees at a rate of Rs 20 for every 50 toffees. Additionally, he bought twice as many toffees at a price of Rs 1.50 per piece. He ...
Consider two natural numbers, 'a' and 'b', which are in the ratio of 17:20. If we increase 'a' by 18 and decrease 'b' by 20, the new ratio of 'a' to 'b'...
Determine the sum of the first 16 odd numbers.
Find the sum of all natural numbers less than 1,000 that are divisible by both 3 and 5 but not by 7.
- Find the sum of all two-digit numbers that are exactly divisible by 7.