Question
‘A’ can finish a project in 40 days, whereas ‘B’ finishes 50% of the project in 12 days less than ‘A’. How many days will it take both ‘A’ and ‘B’ to complete 90% of the project together?
More Time and work Questions
- ‘A’ can complete a job in 36 days. ‘B’ takes 3 times as long as ‘A’ to finish the same job. If both work together, how much of the work will they finish in...
- ‘A’ alone can do some work in 20 days. ‘B’ and ‘C’ together can do the same work in 15 days. If ‘B’ is half as efficient as ‘A’, then find the time taken b...
- ‘A’ can complete a work in 20 days and ‘B’ can complete it in 15 days. Both start together but after 4 days, ‘B’ leaves and ‘A’ finishes the remaining work...
- ‘X’ can finish 50% of a job in 8 days. ‘Y’ takes 8 days more than ‘X’ to complete the entire work, and Y is 20% more efficient than ‘Z’. ‘X’ starts the tas...
- The ratio of efficiencies of Ajay and Bijay is 7:8, respectively. Ajay and Bijay together can complete the total work in 24 days. In how many days will Bij...
- 105 people could complete a work in 36 days. But after they worked together for 7 days their employer wanted the work should be completed in a total of 28 ...
- Two people, A and B, working separately can sanitize a building in 6 and 10 hours, respectively. They work in stretches of one hour alternately. If A begin...
- A takes 24 hours more than B to complete the work, and 32 hours more than C to complete the same work. The combined time taken by A and B to finish the wor...
- Ankit began a task but left it after working for 32 days. The remaining 60% of the task was then completed by Bittu and Sittu working together over 45 days...
- ‘A’ and ‘B’ together can complete a work in 18 days. If ‘A’ increases his efficiency by 20% and ‘B’ decreases his efficiency by 40%, then the time required...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)