      Question

      β€˜A’ can finish a project in 40 days, whereas β€˜B’ finishes 50% of the project in 12 days less than β€˜A’. How many days will it take both β€˜A’ and β€˜B’ to complete 90% of the project together?

      A 21 days Correct Answer Incorrect Answer
      B 15 days Correct Answer Incorrect Answer
      C 34 days Correct Answer Incorrect Answer
      D 25 days Correct Answer Incorrect Answer

      Solution

      Time taken by β€˜B’ to complete the whole work = (40 – 12)/0.5 = 56 days Let the total work = 280 units Efficiency of β€˜A’ = 280/40 = 7 units/day Efficiency of β€˜B’ = 280/56 = 5 units/day Required time taken = {(0.9 Γ— 280)/(7 + 5)} = 252/12 =Β  21 days