Question

‘A’ can finish a project in 40 days, whereas ‘B’ finishes 50% of the project in 12 days less than ‘A’. How many days will it take both ‘A’ and ‘B’ to complete 90% of the project together?

A 21 days
B 15 days
C 34 days
D 25 days