πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      A contractor planned to complete a project in 5 days by employing β€˜a’ workers. But every day exactly 15 workers were absent. As a result, the work got completed in 3/5 more time than usual. Find the value of β€˜a’.

      A 25 Correct Answer Incorrect Answer
      B 40 Correct Answer Incorrect Answer
      C 32 Correct Answer Incorrect Answer
      D 55 Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      ATQ, Usual time = 5 days 3/5 more time than usual β‡’ Actual time = 5 Γ— (1 + 3/5) = 5 Γ— 8/5 = 8 days Total work = a Γ— 5 = (a βˆ’ 15) Γ— 8 So, 5a = 8a βˆ’ 120 3a = 120 a = 40 Therefore, the contractor originally employed 40 workers.

      Practice Next
      More Time and work Questions
      ask-question