Question
A contractor planned to complete a project in 5 days by employing βaβ workers. But every day exactly 15 workers were absent. As a result, the work got completed in 3/5 more time than usual. Find the value of βaβ.
Solution
ATQ, Usual time = 5 days 3/5 more time than usual β Actual time = 5 Γ (1 + 3/5) = 5 Γ 8/5 = 8 days Total work = a Γ 5 = (a β 15) Γ 8 So, 5a = 8a β 120 3a = 120 a = 40 Therefore, the contractor originally employed 40 workers.
More Time and work Questions
- Karan, Arjun and Krunal alone can complete a work in 40, 60 and 48 days respectively. All of them started working together but after 3 days from start Kara...
- Rajesh and Bhupesh can complete a piece of work in 20 days and Bhupesh alone in 25 days. In how many days can Rajesh alone complete the work?
- A worker completes 30% of a job in 6 days. Assuming the same rate of work, in how many total days will he complete the whole job?
- In an office, an employee plans to do a work in 20 days with 6 laptops. But after 10 days, he found that only 40% of the work is done with the laptops work...
- 35 men can complete a piece of work in 40 days. βxβ men started the work and after 30 days 60 more men joined them so that whole work was finished in the d...
- A can complete a piece of work in 24 days. He worked for 21 days and then B finished the remaining work in 6 days. In how many days can A and B finish the ...
- Arjun and Karan can do a work separately in 20 days and 50 days respectively. Arjun started the work and was later joined by Karan. When should Karan join ...
- Working alone, B can complete the work in 30 days. C is twice as efficient as B and A takes 20 days more than it takes C to complete the work. Working toge...
- 50% of the work done by Meena in 2 days is equal to 25% of the work done by Lata in 5 days. If Meena can complete the job alone in 10 days, then how long w...
- Ten men begin to do work. But after some days, four of them left the job. As a result, the job that could have been completed in 40 days is completed in 50...