Question
A and B can complete a piece of work in 12 days and 16 days respectively. They work together for 4 days, and then A leaves. How many more days will B take to finish the remaining work?
More Time and work Questions
- A, B, and C together can complete the assignment in 8 days. B and C together take (48/5) days, and C alone completes half in 8 days. Find the ratio of the ...
- ‘A’ and ‘B’ can do a piece of work in 20 days and 32 days, respectively. If they started the work together and worked on it for 5 days, then find the time ...
- Komal and Seema individually can complete a task in ‘2a’ hours and ‘7a’ hours respectively. If they together can complete half of the work in 7 hours, then...
- 24 men can complete _______% of the whole work in 12 days working 10 hours in a day. 30 men working 8 hours in a daycan complete 30% of the whole work in _...
- A fence is constructed using 900 wooden planks. ‘X’ alone can place 10 planks per minute, while ‘Y’ alone can complete the fence in 100 minutes. ‘Z’, a cur...
- A can fabricate a divider in 15 days , while B alone can assemble it in 25 days, If they construct it together and get an installment of Rs 7000, then find...
- Ajay completes half the work done by Rohit in 5/6 of the time. If they together finish the work in 18 days, how much time will Rohit take to complete the w...
- ‘A’ alone can do some work in 10 days. ‘B’ and ‘C’ together can do the same work in 4 days. If ‘B’ is half as efficient as ‘A’, then find the time taken by...
- A and B individually can complete the work in 28 days and 42 days respectively. If the time taken by C alone to complete the work is 1.25 times the time ta...
- ‘F’ is 66.67% more efficient than ‘G’. ‘G’ worked alone for 10 days, and then ‘F’ completed the rest of the work. If the entire job was finished in 35 days...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)