Question
A is capable of finishing a task in 60 days. B requires
40% more time than A to finish the same task. How many days will A and B need to complete 80% of the work together?Solution
Time taken by B to complete the whole work = 1.40 × 60 = 84 days Let total work = 420 units (LCM of 60 and 84) Efficiency of A = 420/60 = 7 units per day Efficiency of B = 420/84 = 5 units per day Desired time = (0.80 × 420)/12 = 28 days
When is the World Fisheries Day celebrated annually?Â
WWF-India’s Central Indian Satpuda Maikal Landscape (SML) sprawls across 19 districts of which of the following states?
A- Madhya PradeshÂ
...With reference to Critical Minerals for India, consider the following statement:
1.   These are the elements that are the building blocks of ...
Who is often referred to as the "Father of Geography"?
Who has assumed the role of the 26th Director General of the Indian Coast Guard?
In which state did Prime Minister Narendra Modi inaugurate the High-Tech Sports Training Centre?
Who was the Chief Justice of India during the Emergency (1975-1977)?
What was the purpose of the seven-volume series 'Greatness of Spirit' launched by the Ramon Magsaysay Award Foundation?
The salaries of the Supreme Court judges are determined by _______.
Which Indian cricketer was awarded the ICC Men’s Test Cricketer of the Year 2024?