Question

A is capable of finishing a task in 60 days. B requires 40% more time than A to finish the same task. How many days will A and B need to complete 80% of the work together?

A 24 days
B 28 days
C 32 days
D 30 days
E None of these
Practice Next

More Time and work Questions

Hey! Ask a query

🎓
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
  • 200 Questions with Detailed Solutions
  • Section-wise Coverage (GA, English, Quant & Reasoning)