Question
A can finish a work in 25 days and B can complete the
same work in 10 days. B worked for 5 days and left the job. In how many days can A alone finish the remaining work?Solution
A can finish a work=25 days. B can complete the same work=10days. LCM of 25 and 10 =50 Let the total work =50 units Efficiency of A =50/25=2 units Efficiency of B =50/10=5 units B worked for 5 days =5×5=25 units. Remaining work =50-25 =25. Remaining work done by A =25/2 =12.5 days.
What leadership style involves giving employees a high level of independence and decision-making authority?
Neutrality, in the context of international relations, involves:
Why is effective inventory control crucial in stores management?
What is a key characteristic of prudence in decision-making?
What ethical concern arises when a public servant engages in the unauthorized disclosure of classified information?
What does temperance entail in personal behavior?
What activities can aid in the development of emotional intelligence?
What is a key aspect of principled negotiation?
What does maintaining confidentiality mean in a professional setting?
What does dedication to public service entail?