Question
35 people working 7 hours a day take 22 days to complete a task. How many people working for 6 hours a day are needed to complete five times the given task in 40 days if they work at 30% higher efficiency? (can calculate approximate value)
More Time and work Questions
- E and F can complete a task in 24 days together. E alone can do it in 40 days. Find the time F alone would take.
- Pooja used to solve 36 problems in 72 minutes. After her efficiency decreased by 33.33%, how long will she now take to solve the same number of problems?
- A and B together can complete a piece of work in 12 days while A alone can complete 70% of the work in 14 days. Find the time taken by B to complete 80% of...
- ‘A’ and ‘B’ can do a piece of work in 25 days and 30 days, respectively. If they started the work together and worked on it for 8 days, then find the time ...
- ‘X’ and ‘Y’ can do a task together in 15 days. If ‘X’ alone takes 25 days to complete it, then how much time will ‘Y’ take to finish the task alone?
- A team of 12 men and 18 women can complete a construction project in 24 days. If 6 women alone can do the same project in 144 days, how many days will 48 m...
- A can complete a work in 10 days and B can complete it in 15 days. They work together for 4 days, then A leaves. In how many days will B finish the remaini...
- A can do a work in 12 days and B can do it in 18 days. In how many days will they finish together?
- ‘E’ alone completes a task in 28 days. ‘F’ is 10% less efficient than ‘E’. They worked together for 7 days and then ‘E’ stopped. What percentage of the tas...
- A group of 21 boys, each working 6 hours a day, complete a school project in 15 days. How many days will it take for 18 boys, working 5 hours daily, to fin...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt