Question

35 people working 7 hours a day take 22 days to complete a task. How many people working for 6 hours a day are needed to complete five times the given task in 40 days if they work at 30% higher efficiency? (can calculate approximate value)

A 19
B 43
C 22
D 87
Practice Next

More Time and work Questions

Hey! Ask a query

🎓
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
  • 200 Questions with Detailed Solutions
  • Section-wise Coverage (GA, English, Quant & Reasoning)