Question
Krishna can do a piece of work in 25 days. He alone
worked at it for 10 days and then Balram completed alone the rest work in 20 days. In how many days, they will complete the whole work, working together?Solution
Efficiency of Krishna = 100/25 = 4% Work done by Krishna in 10 days = 10/25 × 100 = 40% Remaining work = 60% Efficiency of Balram = 60/20 = 3% Therefore, required number of days = 100/((4+3)) = 100/7 = 14(2/7) days
Select the most appropriate option to substitute the bold segment. If no substitution is required select 'No substitution'.
The player was so exh...
In each of the questions given below, four words are given in bold. These four words may or may not be in their correct position. The sentence is then f...
In the following questions, a few words have been highlighted which may or may not be in their correct position. The sentence is then followed by option...
Given below are a few questions with four highlighted words which may or may not require swapping in order to make sentence contextually and meaningfull...
Select the most appropriate option that can substitute the bold segment in the given sentence. If there is no need to substitute it, select ‘No substi...
In the question given below, four words are given in bold. These four words may or may not be in their correct position. The sentence is then followed...
While travellers going (A) at the airport do not face any slot (B) in online booking for RAT, passengers arriving (C) to countries other than the U.A.E...
Two sentences are given below, with three words emboldened in each of them. Interchange the words between two sentences to form a grammatically and con...
In each of the following question, a sentence is given with four words marked as (A), (B), (C) and (D). These words may or maybe not placed at their co...
(i) While carbon markets came into gain (A) nearly two decades ago, they have been plagued by opacity and criticism that they only created the illusion...