‘Pawan’, ‘Qureshi’, and ‘Ram’ can finish 50%, 1/3, and 3/4 of a job in 24, 18, and 54 days, respectively. If ‘Pawan’ and ‘Qureshi’ start the job together and work on it for 18 days, calculate how long ‘Ram’ will take to complete the remaining work alone.

A 21 days
B 28 days
C 32 days
D 42 days
E None of these