Start learning 50% faster. Sign in now
ATQ,
Let the efficiency of each worker be 'e' units/day
Total work = 16 × 24 × e = 384e units
Work done in 9 days = 16 × 9 × e = 144e units
Remaining work = 384e - 144e = 240e units
Remaining workers = 16 - 6 = 10
Time needed = 240e ÷ (10 × e) = 24 days
Extra days = 24 - 15 = 9 days
Book : Author :: Furniture : ?
Select the option that is related to third cluster in the same way first cluster is related to second cluster.
TURN : 219 :: MAINS: ?
Select the option that is related to the third number in the same way as the second number is related to first number and the sixth number is related to...
In the following question, select the related word pair from the given alternatives.
Wisdom: Knowledge :: Naivety: ?
Select the related number from the given alternatives:
467 : 165 :: 3518: ____
Select the option in which the numbers are related in the same way as the numbers of the following set:
(5, 500, 10)
Select the option that is related to third letter cluster in the same way second letter cluster is related to first letter cluster.
DECIMAL: Z...
Select the related number from the given alternatives:
5 : ? :: 4 : 65
Statements:
Some Necklaces are Rings.
All Rings are Bracelet.
Only a few Rings are Ornaments.
Conclusion:
I. All Brac...
Man : Mammal : : Rat : ?