Question
An organization engaged 16 workers to complete a task in 24
days. After 9 days, 6 workers had to leave unexpectedly. How many additional days will it now take to complete the work?Solution
ATQ,
Let the efficiency of each worker be 'e' units/day
Total work = 16 × 24 × e = 384e units
Work done in 9 days = 16 × 9 × e = 144e units
Remaining work = 384e - 144e = 240e units
Remaining workers = 16 - 6 = 10
Time needed = 240e ÷ (10 × e) = 24 days
Extra days = 24 - 15 = 9 days
In a factory all Tuesdays and Saturdays are offs. If a month starts with a Tuesday and has 31 days then how many offs will be there in that month?
If the day before yesterday was Wednesday, then the day after tomorrow will be:
At what angle the hands of a clock are inclined at 25 minutes past 9?
Which two months in a year have the same calendar?
At 9:45 in a clock, the angle between the minute and hour hands is:
- When seen through a mirror, a clock shows 2:45hrs. The correct time is ___.
- What will be the angle formed between the hour hand and minute hand of a clock at 6:48am?
- It was Thursday on February 8, 2024, then, what will be the day on February 8, 2028?
If it was Sunday on 1st February 2020, then what was the day on 1st October 2020?
What is the reflex angle between the hands of a clock at 8:30?