Question
If ‘X’ finishes a project in 24 days whereas ‘X’
and ‘Y’ working together can finish it in 15 days, then determine the time ‘Y’ alone will take to finish the project.Solution
ATQ,
Let the total work = 120 units {LCM (24 and 15)}
Efficiency of ‘Y’ = (120/24) = 5 units/day
Efficiency of ‘X’ and ‘Y’ together = (120/15) = 8 units/day
Efficiency of ‘Y’ = (8 – 5) = 3 units/day
Time taken by ‘Y’ to complete the project alone = (120/3) = 40 days
Which of the following given options is the plant cell wall mainly consisting of?
Indian Lac Research Institute is located at :
In paddy, the clipping of tip of seedlings is done as a preventive measure against which pest?
Spongilla is the common example which belongs to……………….Phylum of Animal Kingdom.
White rust of crucifer is caused by:
A small structure in mammary glands in which milk is manufactured by female animals is
Gundhi bug, a pest of rice attacks the plant in which stage?
Bean common mosaic disease is caused by
Budding is most commonly done when there is
During meiosis origin of synaptonemal complex occurs in