Question
If ‘X’ finishes a project in 24 days whereas ‘X’
and ‘Y’ working together can finish it in 15 days, then determine the time ‘Y’ alone will take to finish the project.Solution
ATQ,
Let the total work = 120 units {LCM (24 and 15)}
Efficiency of ‘Y’ = (120/24) = 5 units/day
Efficiency of ‘X’ and ‘Y’ together = (120/15) = 8 units/day
Efficiency of ‘Y’ = (8 – 5) = 3 units/day
Time taken by ‘Y’ to complete the project alone = (120/3) = 40 days
The Foreign exchange reserve consists of
The Human Development Index (HDI) was developed by a select team of leading scholars, development practitioners and members of the Human Development re...
DICGC is a wholly-owned subsidiary of ____________.
Consider the following statements with respect to the International Labour Organisation-
I.It is the only tripartite United Nation (UN) agency. I...
Consider the following statement about the Periodic Labour Force Survey (PLFS):
1. It estimates employment and unemployment indicators in both �...
Which of the following can be the outcomes of very high inflation in the economy?
(1) Reduction in economic growth
(2) Increase in savings...
Consider the following statement:
I. DCGI is the central licensing authority for medical devices that fall under the Medical Device Rules 2017.
Which of the following are the benefits of the Pradhan Mantri Jan Arogya Yojana (PMJAY)?
1. Free treatment available at all public and empanelled...
What does the “E” stand for in OECD.
Which of the following Statements about the PM Jeevan Jyoti Bima Yojna is/are not True?
I- In case of the death of the insured person, the next e...