Question
If ‘X’ finishes a project in 24 days whereas ‘X’
and ‘Y’ working together can finish it in 15 days, then determine the time ‘Y’ alone will take to finish the project.Solution
ATQ,
Let the total work = 120 units {LCM (24 and 15)}
Efficiency of ‘Y’ = (120/24) = 5 units/day
Efficiency of ‘X’ and ‘Y’ together = (120/15) = 8 units/day
Efficiency of ‘Y’ = (8 – 5) = 3 units/day
Time taken by ‘Y’ to complete the project alone = (120/3) = 40 days
Consider the following statements:
1. Article 82 of the Indian constitution mandates the Parliament to enact a Delimitation Act after every Cen...
The union government has launched a program to achieve universal immunization. The name of the program is
Which ports belong to the western coast of India?
"New Population Bomb" means :
Identify India's rank as a global silk producer.
Which of the following district/s is/are not shared its boundary with “Nepal”?
I. Balarampur
...Select the false statement related to PM Kisan Samman Nidhi Yojana:
Which of these countries will be the guest of honour in 6th edition of World Government Summit in Dubai, UAE?
RBI does not manage/influence?
The headquarter of International Cricket Council is located at