Question
If ‘X’ finishes a project in 24 days whereas ‘X’
and ‘Y’ working together can finish it in 15 days, then determine the time ‘Y’ alone will take to finish the project.Solution
ATQ,
Let the total work = 120 units {LCM (24 and 15)}
Efficiency of ‘Y’ = (120/24) = 5 units/day
Efficiency of ‘X’ and ‘Y’ together = (120/15) = 8 units/day
Efficiency of ‘Y’ = (8 – 5) = 3 units/day
Time taken by ‘Y’ to complete the project alone = (120/3) = 40 days
Who was the Governor-General of India during the Revolt of 1857?
When will the revised National Pension Scheme (NPS) be implemented in Maharashtra, aligned with the Union government's Unified Pension Scheme (UPS)?
How many candidates were considered for selection in the HOPE station Mars simulation before final two participants were chosen?
What was the focus of the conference organized at Kochi?
Axis Bank has signed a memorandum of understanding (MoU) with the ______ Police, offering a package with benefits and features under ''Power Salute'', ...
Which ministry organized the LEAPS (Logistics Excellence, Advancement, and Performance Shield) Valedictory Session in New Delhi?
With reference to the Contingent Risk Buffer (CBR), consider the following statements:
1. Reserve Bank of India will transfer Rs 30,307 crore a...
Who took over as the new President of the Indian Chamber of Commerce (ICC) in 2024?
- What new name has been given to Fort William in Kolkata?
Who was appointed Executive Director of RBI on 9 October 2025?