Question
Anu can finish 25% of an assignment in 10 days, whereas
Tanya can do 30% in 12 days. Anu works on it for 16 days and leaves. How long will Tanya take to wrap up the remaining work?Solution
ATQ,
Time taken by Anu to complete whole work = (10 / 0.25) = 40 days
Time taken by Tanya to complete whole work = (12 / 0.30) = 40 days
Let the total work be 120 units (LCM of 40 and 40)
Efficiency of Anu = (120 / 40) = 3 units/day
Efficiency of Tanya = (120 / 40) = 3 units/day
Work completed by Anu in 16 days = 16 × 3 = 48 units
Remaining work = 120 - 48 = 72 units
Therefore, required time = (72 / 3) = 24 days
The President gives his resignation to the:Â
Professional communications are now covered under which section of BSA?
Section 87 of Indian Evidence Act, 1872, provides:-
Section 9(3) of the Environment (Protection) Act, 1986 allows recovery of remedial expenses together with interest at such reasonable rate as the Govern...
Which of the following rights are granted to all citizens of India under the Constitution?
As per section 408 of the Companies Act the National Company Law Tribunal shall consist of ________________
Section 8(1)(g) empowers the Commission to tender advice to Central Government, corporations etc. on matters:
Suit against a trustee of a temple for account of trust property and proceeds thereof-
Which principle states that the trustee must act honestly and in good faith, prioritizing the interests of the beneficiaries above their own?
What occurs to the employment status of officers and employees of an existing insurer who were primarily engaged in general insurance business on the ap...