Question
Anu can finish 25% of an assignment in 10 days, whereas
Tanya can do 30% in 12 days. Anu works on it for 16 days and leaves. How long will Tanya take to wrap up the remaining work?Solution
ATQ,
Time taken by Anu to complete whole work = (10 / 0.25) = 40 days
Time taken by Tanya to complete whole work = (12 / 0.30) = 40 days
Let the total work be 120 units (LCM of 40 and 40)
Efficiency of Anu = (120 / 40) = 3 units/day
Efficiency of Tanya = (120 / 40) = 3 units/day
Work completed by Anu in 16 days = 16 × 3 = 48 units
Remaining work = 120 - 48 = 72 units
Therefore, required time = (72 / 3) = 24 days
What should come in place of (?) question mark in the given number series.
81, 73, 66, 60, 55, ?
14 6 4 4 ? 48
...What should come in place of (?) question mark in the following number series.
5, 11, 23, 47, 95, ?
In each of the following number series, one term is missing. Find the missing term.
1, 4, 9, 16, 25, ?
What will come in place of the question mark (?) in the following series?
4, 11, 32, 95, 284, 851, ?
156, 182, 210, 240, 272, ?
31    32      35      ?      47       56
...What should come in place of (?) question mark in the following number series.
1, 2, 6, 24, 120, ?
What value should come in the place of (?) in the following number series?
71, 72, 76, 103, ?, 244254, ?, 1022, 1150, 1214, 1246