Question
A can do a work in 45 days and the sameĀ the work is
done in 15 days by A and B together, then in how many days B can complete the 20% of work?Solution
A takes 45 days A and B together takes 15 days LCM of 45 and 15 = 45 units Efficiency of A = 45/45 = 1 Efficiency of A and B = 45/15 = 3 Ā So, efficiency of B = 3 ā 1 = 2 B does 20% of the total work. Then, 20% of 45 = 9 units So, B will take 9/2 = 4.5 days to complete the work.
Where is the headquarters of the Indian Science Congress Association situated?
Ā Chandrayaan -3 is all set to be launched in the month of ______ in 2023?
The Pradhan Mantri Mudra Yojana (PMMY) loan limit was increased to which amount?
What is the name of the former Argentina footballer who passed away recently?Ā
Despite a decrease in agriculture exports, which position did India retain in global agriculture exports in 2023 according to the WTO?
Which of the following was NOT one of the three initiatives celebrated by MoHUA on its 9th anniversary?
What is the name of Belgiumās world-first green energy island project?
When is International Human Solidarity Day observed?
Which country is leading the Multinational Security Mission (MSS) approved by the United Nations Security Council to address the escalating gang violenc...
What unique requirement is mandated for political parties fielding candidates with criminal backgrounds, as facilitated by the 'Know Your Candidate' (KY...