Question
A can complete a work in 15 days. B takes 6 days less
than A to complete the same work. In how many days can both of them together complete 80% of the work together?Solution
Time taken by B to complete the work = 15 – 6 = 9 days Let the total work = 45 units Efficiency of A = 45/15 = 3 units/day Efficiency of B = 45/9 = 5 units/day Required time taken = 0.80 x 45/(3+5) = 4.5 days
Statements: L < E; M = O; E >K ≥ M
Conclusions:
I. L < M
II. K = O
In the following question the relationship between different elements is given in the statements followed by three conclusions I, II and III. Read the ...
Statements: J # Q, Q * D, D % P, P $ Y
Conclusions:Â Â Â Â Â Â I. Q * YÂ Â Â Â Â Â Â Â Â Â Â Â Â Â Â II. P *YÂ Â Â Â Â Â Â Â Â Â Â Â Â Â Â III...
Statements: J < K, J < L, L > M
Conclusions: I. J < M II. L = J
...Statements: J ≤ K = L ≤ N; N ≤ O = M
Conclusions: I. M = JÂ Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â II. J < M
...Statements: Q % R & L @ T $ D; W % Q # P
Conclusions :Â Â Â Â Â I. D % RÂ Â Â Â Â Â Â Â Â Â Â Â Â Â Â II. Q % LÂ Â Â Â Â Â Â Â Â Â Â Â Â Â I...
In the following question the relationship between different elements is given in the statements followed by three conclusions I, II and III. Read the ...
Which among the following symbols should replace the question mark [?] (in the same order from left to right) in the given expression in order to make b...
In the question, assuming the given statements to be true, find which of the following conclusion(s) among the two conclusions is/are true and then gi...
In the following question the relationship between different elements is given in the statements followed by three conclusions I, II and III. Read the ...