A can complete a work in 15 days. B takes 6 days less than A to complete the same work. In how many days can both of them together complete 80% of the work together?

A 8 days Correct Answer Incorrect Answer
B 3 days Correct Answer Incorrect Answer
C 10 days Correct Answer Incorrect Answer
D 4.5 days Correct Answer Incorrect Answer
E None of these Correct Answer Incorrect Answer

Solution

Time taken by B to complete the work = 15 – 6 = 9 days Let the total work = 45 units Efficiency of A = 45/15 = 3 units/day Efficiency of B = 45/9 = 5 units/day Required time taken = 0.80 x 45/(3+5) = 4.5 days