P and Q can complete a work in 30 days and 45 days,
respectively. P, Q and R together can complete the work in 15 days. If R get a total wage of Rs. 5400 to complete the work alone, then find the per day wage of R.Solution
Let the total work be LCM of (30, 45 and 15) = 90 units Number of units of work done by P alone in one day = 90/30 = 3 units Number of units of work done by Q alone in one day = 90/30 = 2 units Number of units of work done by P, Q and R together in one day = 90/15 = 6 units Number of units of work done by R alone in one day = 6 – 3 – 2 = 1 unit So, time taken by R alone to complete the work = 90/1 = 90 days So, per day wage of R = 5400/90 = Rs. 60
The Mehrangarh Fort is located at which city of Rajasthan?
Which of the following is NOT a pillar of Mission Karmayogi?
What is the primary focus of SEBI's newly launched Foreign Portfolio Investor (FPI) outreach cell?
 Mortgage loan housing finance sole proprietary of which organization?
Consider the following statements regarding the Harappan Civilization:
1. The Harappan Civilization flourished in Sindh and Punjab.
2. It ...
In which of the following year was the Tata Iron and Steel Company established?
The single policy rate now is -
Which state has the largest castor cultivation area in India?
Who has been appointed as the Chief Executive Officer (CEO) of UIDAI on 2 January 2025?
Sulochana Chavan passed away at the age of 92 years she was famous?