Question

P and Q can complete a work in 30 days and 45 days, respectively. P, Q and R together can complete the work in 15 days. If R get a total wage of Rs. 5400 to complete the work alone, then find the per day wage of R.

A Rs. 60
B Rs. 80
C Rs. 65
D Rs. 70