    Question

    A team of 12 men and 18 women can complete a

    construction project in 24 days. If 6 women alone can do the same project in 144 days, how many days will 48 men take to complete the project alone?
    A 40 Correct Answer Incorrect Answer
    B 24 Correct Answer Incorrect Answer
    C 30 Correct Answer Incorrect Answer
    D 15 Correct Answer Incorrect Answer
    E None of these Correct Answer Incorrect Answer

    Solution

    ATQ, Task done by 6 women in 1 day = 1/144 Task done by 18 women in 1 day = 3/144 = 1/48 Task done by 12 men = 1/24 – 1/48 = 1/48 Task done by 48 men = 4/48 = 1/12 Hence, required time = 12 days