Question
A team of 12 men and 18 women can complete a construction project in 24 days. If 6 women alone can do the same project in 144 days, how many days will 48 men take to complete the project alone?
More Time and work Questions
- A can complete a work in 18 days , B in 24 days , and C in 36 days . A starts the work alone and works for 4 days . Then B joins him, and after 3 more...
- A is 50% more efficient than B. A and B together can complete a piece of work in 20 days. Both of them started working together and worked for 12 days, aft...
- 'R' takes 20 days to complete a task, and 'A' takes 30 days to do the same task. To finish the job in just 6 days, what percentage increase in their respec...
- ‘X’ and ‘Y’ together can complete a work in 10 days, while ‘Y’ and ‘Z’ together can complete the work in 8 days. If ‘Y’ takes 12 days to complete the work ...
- P and Q can complete a piece of work individually in 12 days and 20 days, respectively. They start working together, but after 6 days, Q leaves the work. P...
- ‘M’ is 60% more efficient than ‘N’. ‘N’ started the work alone and worked for 20 days and after that ‘N’ is replaced by ‘M’. If the total work is completed...
- Two workers A and B were put to some work. If A worked alone, he would have taken 8 hours more than when both A and B had worked together. If B worked alon...
- A worker finishes 40% of a job in 6 days. At the same rate, how many more days are needed to finish the remaining work?
- If Arjun can complete his work in 28 days by working 4 hours a day, how many hours a day should he work to finish the same work in 16 days?
- A and B together have to complete a piece of work consisting of 160 equal units. A can do (x + 2) units of work per day and B can do (x − 2) units per day....
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)