Question
'Sunil', 'Arjun', and 'Rahul' can complete a task
individually in 45, 60, and 90 days respectively. All began the work together, but Sunil and Arjun left 11 and 6 days before work completion respectively. Calculate the total time to finish the task. (Calculate approximate value)Solution
ATQ,
Let the total work be 180 units (LCM of 45, 60, 90)
Efficiency of Sunil = 180 / 45 = 4 units/day
Efficiency of Arjun = 180 / 60 = 3 units/day
Efficiency of Rahul = 180 / 90 = 2 units/day
Let total time = n days
(4 + 3 + 2)(n - 11) + (3 + 2)(5) + 2(6) = 180
Or, 9n - 99 + 25 + 12 = 180
Or, 9n = 242
So, n = 242 / 9 = 26.88 ≈ 27 days
What is the unit of measurement for the intensity of sound?
The resolution related to the removing of Vice-President of India can be moved in the
The Programme which was launched in 2005-06, to provide basic amenities and infrastructure to rural India is called as :
Match the following awards 2019:
(a) Best Translator Award                              1. Pulavar V. Prabhakar...
As per ______, the President shall address both Houses of Parliament assembled together on the commencement of the first parliament session of each year.
'Mission Palanhar' has been launched by which district administration to connect the underprivileged people with the Palanhar scheme?
Which Rajasthan minister has been given the 'Leader of Decade' award by the Women Economic Forum?
Which of the following is a Regional Party of Karnataka?
Which saint composed 'Sant Gun Sagar' and 'Naam-Maala' ?
_____________ is the scheme for the scavengers and their dependents to form self help groups and get loans with subsidies.