Question
'Sunil', 'Arjun', and 'Rahul' can complete a task
individually in 45, 60, and 90 days respectively. All began the work together, but Sunil and Arjun left 11 and 6 days before work completion respectively. Calculate the total time to finish the task. (Calculate approximate value)Solution
ATQ,
Let the total work be 180 units (LCM of 45, 60, 90)
Efficiency of Sunil = 180 / 45 = 4 units/day
Efficiency of Arjun = 180 / 60 = 3 units/day
Efficiency of Rahul = 180 / 90 = 2 units/day
Let total time = n days
(4 + 3 + 2)(n - 11) + (3 + 2)(5) + 2(6) = 180
Or, 9n - 99 + 25 + 12 = 180
Or, 9n = 242
So, n = 242 / 9 = 26.88 ≈ 27 days
The declining number of public-transport buses in Kerala has __________ in availability of buses ___________ to approximately 0.50 per 1,000 people, as ...
Choose the correct answer to fill the given blank
The teacher asked the students _____ their homework.
Fill in the blanks:
The owner was ____________when he _____________that his expensive flower was eaten for lunch.
He uses simple lines and bright colours _________ detailed illustrations.
- In the following sentence, there is a blank space. Below each such sentence, there are four options with one word each. Fill up the blank with the word tha...
Directions : In each of the following questions a sentence is given with one blank. You have to fill the blank with one of the words given as options i...
Fill in blank 60 with the most appropriate word.
Legend _____ be a shadow ______ the past.
Each question below has two blanks, which is indicating that something has been omitted. Choose the most suitable option indicating the words that can ...
The boys had just ________ their first bite, when they ____________ a sobbing sound ________ from the other side of some bushes. Dan ran _____ the sound...