Question
'Sunil', 'Arjun', and 'Rahul' can complete a task
individually in 45, 60, and 90 days respectively. All began the work together, but Sunil and Arjun left 11 and 6 days before work completion respectively. Calculate the total time to finish the task. (Calculate approximate value)Solution
ATQ,
Let the total work be 180 units (LCM of 45, 60, 90)
Efficiency of Sunil = 180 / 45 = 4 units/day
Efficiency of Arjun = 180 / 60 = 3 units/day
Efficiency of Rahul = 180 / 90 = 2 units/day
Let total time = n days
(4 + 3 + 2)(n - 11) + (3 + 2)(5) + 2(6) = 180
Or, 9n - 99 + 25 + 12 = 180
Or, 9n = 242
So, n = 242 / 9 = 26.88 ≈ 27 days
A want becomes a demand only when it is backed by the
The word ‘BUDGET’ was taken from the _________ word.
When unemployment of potential workers that is not reflected in official unemployment statistics, due to the way the statistics are collected, it is kn...
What does an Inverted Duty Structure imply under the GST framework?
The Marginal cost of production of a commodity is
Which of the following is not a primary function of the Reserve Bank of India (RBI).
In which year was the Fiscal Responsibility and Budget Management (FRBM) Act enacted?
The production function of a firm is a relationship between which two factors?
What does 'VAT' stand for in the context of taxation?
Farming large areas with minimal labor and capital inputs is known as: