Question
20 men can complete a piece of work in 40 days. ‘x’
men started the work and after 35 days 64 more men joined them so that whole work was finished in the desired time. Find the value of ‘x’Solution
Total work = 20 × 40 = 800 units According to question; 35 × x + 5 × (x + 64) = 800 Or, 35x + 5x + 320 = 800 Or, 40x = 480 Or, x = 12
Khadi and Village Industries Commission (KVIC) has cancelled the “Khadi Certification” of its oldest Khadi Institution named ...
What is the maximum equity allocation allowed under the LC75 investment option?
IFFCO will collaborate with ________ will manufacture Nano DAP for a period of three years.
What is the official name of the High Seas Treaty signed under UNCLOS?
What is the World Bank’s revised South Asia growth forecast for 2026?
Who has been roped as the New Managing Director of Delhi Metro Rail Corporation (DMRC)?
_______ has developed the country's first smartphone-based e-voting solution.
Under the Public Distribution System which of the following is not being allocated to the States/UTs for distribution form union government?
Kathmandu has been identified as the most polluted city in the world. What percentage has air pollution reduced the average life expectancy in Kathmandu?
What contributed to the record ₹1.78 lakh crore profit by Public Sector Banks (PSBs) in FY25?