Question
If 24 persons can finish 50% of work in 12 days in how
many days 48 person can finish the complete work?Solution
let the total work =1 M1 D1 H1/W1 = M2 D2 H2/W2 24×16 / (1/2) =48×D2 /1 D2 =16days.