📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!


    âš¡ Azaadi sale - Celebrate Independence Day with Flat 55% Off On all courses! 13 to 17 Aug âš¡ Enroll Now

    Question

    If 24 persons can finish 50% of work in 12 days in how

    many days 48 person can finish the complete work?
    A 16days Correct Answer Incorrect Answer
    B 12days Correct Answer Incorrect Answer
    C 8days Correct Answer Incorrect Answer
    D 10days Correct Answer Incorrect Answer

    Solution

    let the total work =1 M1 D1 H1/W1 = M2 D2 H2/W2 24×16 / (1/2) =48×D2 /1 D2 =16days.

    Practice Next
    ask-question

    Not sure which exam is best for you Talk to our expert

    Get My Free Call