Question
P alone can finish a piece of work ‘M’ in 6 days
while Q takes 3 days to finish it alone. P, Q and R working together can finish the work ‘N’ which is 10 times of work ‘M’ in 4 days. How long will R take to finish work ‘N’, when working alone?Solution
Let the work ‘M’ = 6 units (LCM of 6 and 3) Efficiency of P = 6/6 = 1 units Efficiency of Q = 6/3 = 2 units Efficiency of P, Q and R = (6 × 10)/4 = 15 units per day Efficiency of R = 15 – (1 + 2) = 12 units per day Time taken by R to finish work ‘N’ = 60/12 = 5 days
Iron was proved to be essential for plants by:
The Nobel Prize in Physiology or Medicine 1948 was awarded to Paul Hermann Müller for his
discovery of which high efficiency contact poison ag...
The NaMo Shetkari Mahasanman Nidhi Yojana is a scheme launched by the Government of ________to provide financial assistance to farmers in the state. The...
Which soil is developed in areas with high temperature and heavy rainfall?
Light-stable synthetic pyrethroids, which is registered to control mites
Which one is the first crop plant whose whole genome was sequenced in 2010.
Loose smut in wheat can be effectively controlled by
Which scheme aims to provide “Housing for All” by constructing houses for rural poor families?
______ is a statement of situation, objectives, problems & solutions.
Soil fertility does not depend on: