Question
P alone can finish a piece of work ‘M’ in 5 days while Q takes 3 days to finish it alone. P, Q and R working together can finish the work ‘N’ which is 11 times of work ‘M’ in 5 days. How long will R take to finish work ‘N’, when working alone?
More Time and work Questions
- In an office, an employee plans to do a work in 20 days with 6 laptops. But after 10 days, he found that only 40% of the work is done with the laptops work...
- Ajay completes half the work done by Rohit in 5/6 of the time. If they together finish the work in 18 days, how much time will Rohit take to complete the w...
- A and B together can complete a piece of work in 30 days while A alone can complete 50% of the work in 20 days. Find the time taken by B to complete 70% of...
- 5 men and 6 women can do some work in 3 days. If each man is 100% more efficient than a woman, then find the time taken by 12 men to finish the same work t...
- If 6 women can complete a work in 3 days, and 9 girls can complete the same work in 2 days, then find the time taken to complete the same work by 8 women a...
- A and B individually can complete the work in 28 days and 42 days respectively. If the time taken by C alone to complete the work is 1.25 times the time ta...
- A can complete a piece of work in 12 days , and B can complete it in 18 days . They work together for 4 days , and then A leaves. In how many more days...
- A and B together can do a work in 10 days, B and C can do together in 5 days while C and A together can do in 12 days. In how many days C alone will comple...
- Working alone, B can complete the work in 25 days. C is twice as efficient as B and A takes 2.5 days more than it takes C to complete the work. Working tog...
- A can fabricate a divider in 20 days , while B alone can assemble it in 30 days, If they construct it together and get an installment of Rs 6000, then find...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)