πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      P alone can finish a piece of work β€˜M’ in 12 days

      while Q takes 8 days to finish it alone. P, Q and R working together can finish the work β€˜N’ which is 10 times of work β€˜M’ in 12 days. How long will R take to finish work β€˜N’, when working alone?
      A 16 days Correct Answer Incorrect Answer
      B 15 days Correct Answer Incorrect Answer
      C 13.5 days Correct Answer Incorrect Answer
      D 12 days Correct Answer Incorrect Answer
      E 14 days Correct Answer Incorrect Answer

      Solution

      Β Let the work β€˜M’ = 24 units (LCM of 12 and 8) Efficiency of P = 24/12 = 2 units Efficiency of Q = 24/8 = 3 units Efficiency of P, Q and R = (24 Γ— 10)/12 = 20 units per day Efficiency of R = 20 – (2 + 3) = 15 units per day Time taken by R to finish work β€˜N’ = 240/15 = 16 days

      Practice Next
      More Time and work Questions

      Relevant for Exams:

      ask-question