      Question

      A contractor undertook to make 20 km of roadway in 48

      weeks. In 28 weeks, 8 km was completed by 120 men working 12 hours a day. The men then agreed to work 3 hour a day overtime and some women were engaged to assist them, the work was finished in the stipulated time. How many women were employed, if the work of 8 men is equal to that of 5 women.
      A 45 Correct Answer Incorrect Answer
      B 51 Correct Answer Incorrect Answer
      C 62 Correct Answer Incorrect Answer
      D None of the above Correct Answer Incorrect Answer

      Solution

      8M = 5W So M/W = 5/8 By M1D1H1/W1 = M2D2H2/W2 (120M ร— 12 ร— 28)/8 = [(120M + xW) ร— 15 ร— 20]/12 (120ร—5 ร— 12 ร— 28)/8 = [(120ร—5ย + xร—8) ร— 15 ร— 20]/12 28ร—3ร—12 = 600 +8x ย  8x = 1008 - 600 = 408ย  So x = 408/8 = 51