The efficiency of P, Q, R, S are in the ratio of
6:5:4:3. If P and R can do a work together in 6 days. Then How many days Q and S will take to complete the same work?Solution
Efficiency of (P+R) = (6+4) = 10 Days taken by (P + R) together to complete the work = 6 days Efficiency of (Q + S) = (5+3) = 8 So, Q and S will take time = (Total days of (P + R) × Total Efficiency of (P + R)) / (Total Efficiency of (Q + S)) = (6 ×10)/8 = 60/8 = 7(1/2) days
Who among the following is not one of the eligible beneficiaries of PMUY?
What is the basic difference between Gross NPA and Net NPA?
I- Gross NPA is the total of Bank loans and Net NPA is the total of all kinds of loan...
Which of the following Statements about IREDA is/are True?
I- It is registered as Non-Banking Financial Company (NFBC) with Reserve Bank of India...
When Government expenditure is more than income, through which of the following ways, it does the deficit financing?
(1) From Banks
(2) Fr...
Which of the following Statements about Multiplier Effect is/are True?
I- When the government spends a rupee, overall income rises by a multiple ...
Which of the following statements about Prompt Corrective Action is/are True?
I-Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Prompt Corrective Action F...
Consider the following statements regarding Phase II of the Swachh Bharat Mission (Grameen) [SBM (G)]
1) The program will be implemented...