Question
A is five times as efficient as B and can finish a piece of work in 24 days less than
A is five times as efficient as B and can finish a piece of work in 24 days less than
B. B can finish this work in how many days?
More Time and work Questions
- John, Emily, and Michael can each complete a task in 15 days, 20 days, and 18 days, respectively. They decide to work on the task alternately, starting wit...
- A man does double the work done by a boy in the same time. The number of days that 3 men and 4 boys will take to finish a work which can be done by 10 men ...
- 'Ramesh' can complete a work in 40 days. He started the work and left after 24 days from starting. The remaining work was done by 'Suresh' in 30 days. Find...
- A work can be completed by ‘A’ and ‘B’, alone in 15 days and 10 days, respectively. Find the number of days taken by ‘C’ to complete the same work alone if...
- The efficiency ratio of Neha, Karan, and Ishaan is 16:11:14, respectively. Together, they can complete a task in 30 days. Neha and Karan started the task, ...
- 'A' and 'B' together can do a piece of work in 12 days while 'B' and 'C' together can do the same work in 20 days. 'A' started the work alone and worked on...
- A can copy 70 pages in 25 hours, A and B together can copy 135 pages in 25 hours. Then in how many hours B can copy 10 pages.
- A and B can complete a task in 63 days and 42 days, respectively. If C is 40% more efficient than the combined efficiency of A and B, how much time will C ...
- A and B together can complete a piece of work in 12 days. B and C together can complete the same work in 15 days, and A and C together can complete it in 2...
- Arjun, Bharat and Chintu together can complete a task in 8 days. Bharat is 25% less efficient than Arjun. Arjun and Chintu together can complete the task i...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt