Question
25 men and 45 women can complete a piece of work in 15
days, while 15 men and 60 women can complete it in 20 days. In how many days can 69 men and 67 women complete the workSolution
25M + 45W =15 days  Þ 5M + 9W = 75 days  15 M + 60W = 20 days  Þ 1M + 4W ® 300 days 300(1M + 4W) = 75(5M + 9W)   4M + 16W = 5M + 9W  7W = M W /M=1/7 Total work = 300 × (7 + 4) = 3300 units Now- 69 man + 67 women = 3300 / (69 × 7 + 67) = 6 days
Which of the following tea estates and their location is not correctly matched:
Which canal serves as a shortcut for maritime trade between Europe and Asia?
Consider the following statements about Defence Acquisition Council (DAC):
1. It is the highest decision-making body of the Defence Ministry on p...
By what amount has the Indian government decided to increase its grant assistance for the enhancement of school infrastructure in the plantation sector ...
What was the primary aim of the significant meeting between India and the UAE about the India-Middle East-Europe Economic Corridor (IMEEC)?
Identify the flag bearer for India at the Paris 2024 Olympics Closing Ceremony.Â
How much is the total loan amount provided by World Bank and ADB for the Amaravati project?
What significant protest did RAS aspirants undertake in June 2025?Â
Which country to host the 5th World Coffee Conference ?
Omar Abdullah has become the new Chief Minister of which of the following?