Question
25 men and 45 women can complete a piece of work in 15 days, while 15 men and 60 women can complete it in 20 days. In how many days can 69 men and 67 women complete the work
More Time and work Questions
- Avinash is twice as good as Bhuvanesh and together they can finish a job in 50 days. Bhuvanesh will finish the work alone in how many days?
- P and Q can complete a work in 28 days and 42 days, respectively. P, Q and R together can complete the work in 14 days. If R get a total wage of Rs. 5460 t...
- ‘A’ can do a piece of work in 15 days. ‘B’ can do 70% of the same work in 20 days. If they work together for the entire time and ge...
- A can complete a work in 10 days and B can complete it in 15 days. In how many days will they complete the work together?
- A person travelled for the first 150 km at a certain speed in 6 hours. After that, the speed of the person decreased by 6 km/h. If the person took a total ...
- A man can complete a task in 20 days, a woman can finish it in 30 days, and a boy can do the same task in 60 days. To complete the task in just 3 days, how...
- 50% of the work done by Meena in 2 days is equal to 25% of the work done by Lata in 5 days. If Meena can complete the job alone in 10 days, then how long w...
- 40 men can complete a piece of work in 40 days. ‘x’ men started the work and after 30 days 64 more men joined them so that whole work was finished in the d...
- A can finish a work in 12 days and B can finish the same work in 18 days. They work together for 4 days and then B leaves. In how many more days can A alon...
- 28 men can complete a piece of work in 12 days. 12 men started the same work and worked for 10 days, and then joined by ‘x’ more men such that the remainin...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt