Question
‘A’ and ‘B’ can do a piece of work in 30 days
and 20 days, respectively. If they started the work together and worked on it for 4 days, then find the time taken by ‘B’ alone to complete the remaining work.Solution
Let total amount of work be 60 units Efficiency of ‘A’ = 60/30 = 2 units/day Efficiency of ‘B’ = 60/20 = 3 units/day Amount of work done by ‘A’ and ‘B’ together in 4 days = (2 + 3) × 4 = 20 units Time taken by B to complete remaining work = (60 – 20)/3 = 40/3 days
The Pradhan Mantri Kisan Samman Nidhi (PM-KISAN) scheme was launched in which year?
What key area is the MoPR-IIM Ahmedabad training program focused on?
- Who was appointed as the Chairperson of the Airports Economic Regulatory Authority Appellate Tribunal (AERAAT) in March 2025?
- Who won the 2025 Laureus World Comeback of the Year Award?
CRISPR technology is used for:
Which government body is primarily responsible for implementing the SVAMITVA scheme?
By what date has the RBI mandated the implementation of a beneficiary account name look-up feature for RTGS and NEFT transactions?
India signed a $750 million currency swap agreement with which country to help manage its foreign currency crunch?
India is set to submit updated NDCs at COP30 in Brazil. What was India’s earlier pledge on emissions intensity reduction (from 2005 baseline) by 2030?...
- Which country recently surpassed Germany to become the third-largest economy in the world?