Question
‘A’ and ‘B’ can do a piece of work in 30 days
and 20 days, respectively. If they started the work together and worked on it for 4 days, then find the time taken by ‘B’ alone to complete the remaining work.Solution
Let total amount of work be 60 units Efficiency of ‘A’ = 60/30 = 2 units/day Efficiency of ‘B’ = 60/20 = 3 units/day Amount of work done by ‘A’ and ‘B’ together in 4 days = (2 + 3) × 4 = 20 units Time taken by B to complete remaining work = (60 – 20)/3 = 40/3 days
हाल ही में संपन्न हुए हॉकी एशिया कम में भारत ने किस देश क�...
The International Tiger day is observed on
Inventory Turnover measures the relationship of inventory with:
In which year was the recommendation for the establishment of the Indian Environment Service (IES) made by a committee headed by former Cabinet Secretar...
Navegaon National Park is located in which state?
3rd meeting of Council of Trade Development and Promotion held in;
In case of Forward Rate Agreement there is an exchange of interest rate
___________ will sell 6% stake in SBI Mutual Funds which is a joint venture between State Bank of India and France’s Amundi Asset management.
Who among the following inaugurated an advanced electronic surveillance system along the 61-km India-Bangladesh border in Dhubri district of Assam in 2019?
WEF ranked India at which place on the Inclusive Development Index ?