πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      β€˜A’ and β€˜B’ can do a piece of work in 12 days

      and 15 days, respectively. If they started the work together and worked on it for 2 days, then find the time taken by β€˜B’ alone to complete the remaining work.
      A 11.5 days Correct Answer Incorrect Answer
      B 12.5 days Correct Answer Incorrect Answer
      C 10.5 days Correct Answer Incorrect Answer
      D 14.5 days Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      Let total amount of work be 60 unitsΒ  Efficiency of β€˜A’ = 60/12 = 5 units/day Efficiency of β€˜B’ = 60/15 = 4 units/day Amount of work done by β€˜A’ and β€˜B’ together in 2 days = (5 + 4) Γ— 2 = 18 units Time taken by B to complete remaining work = (60 – 18)/4 = 10.5 days

      Practice Next

      Relevant for Exams:

      ask-question