Question
‘A’ and ‘B’ can do a piece of work in 12 days
and 15 days, respectively. If they started the work together and worked on it for 2 days, then find the time taken by ‘B’ alone to complete the remaining work.Solution
Let total amount of work be 60 units Efficiency of ‘A’ = 60/12 = 5 units/day Efficiency of ‘B’ = 60/15 = 4 units/day Amount of work done by ‘A’ and ‘B’ together in 2 days = (5 + 4) × 2 = 18 units Time taken by B to complete remaining work = (60 – 18)/4 = 10.5 days
In the question given below, some sentences/phrases are given which have to be arranged in a proper sequence. Select the option that best defines the p...
What sentences should come 5th in the paragraph?
Select the option that gives their correct ordes.
A.The Qutub Minar is one of the most important monuments in Delhi .
B.Was it just built ...
Which of the following would be the THIRD statement after rearrangement?
Given below are four jumbled sentences. Out of the given options pick the one that gives their correct order.
A. As he looked at them, their head...
Select the most appropriate sequence from the given options to make a meaningful paragraph from jumbled sentences.
A. It is because nowadays pe...
Which of the following would be FOURTH the statement after rearrangement?
Which of the following would be THIRD the statement after rearrangement?
Which of the following would be SECOND the statement after rearrangement?
Given below are four jumbled sentences. Out of the given options pick the one that gives their correct order.
A. Later, they set up their own art...