      Question

      A buffalo alone can plough field β€˜A’ in 30 days. A

      Bull alone can plough the field β€˜A’ in 50 days. Find the number of days taken by 2 bulls and 1 buffalo to together plough field β€˜B’ that is 10% larger than field β€˜A’?
      A 15 days Correct Answer Incorrect Answer
      B 10 days Correct Answer Incorrect Answer
      C 12 days Correct Answer Incorrect Answer
      D 16 days Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      Let the total work done to plough field β€˜A’ = 150 units (LCM of 30 and 50) Then, efficiency of a buffalo = (150/30) = 5 units/day Efficiency of a bull = (150/50) = 3 units/day Total work required to plough field β€˜B’ = 150 Γ— 1.1 = 165 units Combined efficiency of 2 bulls and a buffalo = 3 Γ— 2 + 5 = 11 units So, number of days required to plough field β€˜B’ = 165/11 = 15 days