Question
'G', 'H', and 'I', working together, can finish a task in 6 days. 'G' and 'H' can do it in 7.2 days, and 'H' and 'I' in 9 days. How long would it take for 'H' alone to complete the task?
More Time and work Questions
- A, B, and C each have different rates of completing a task; A can finish it in 36 days, B in 60 days, and C in 30 days. Initially, they begin the work coll...
- Anand and Manav can collaboratively finish a task in {40/3} days, while Anand alone requires 24 days to complete the same task. Given that Prachi's efficie...
- In an office, an employee plans to do a work in 12 days with 4 laptops. But after 4 days, he found that only 40% of the work is done with the laptops worki...
- John, Emily, and Michael can each complete a task in 15 days, 20 days, and 18 days, respectively. They decide to work on the task alternately, starting wit...
- . If 3 goats or 5 sheep can graze a field in 56 days, then in how many days can 6 goats and 10 sheep graze the same field?
- Aman can complete a task in 12 days, while Bhanu alone can complete the same task in 18 days. Aman starts the work alone and continues for 4 days. Then, Bh...
- Working together, Amit and Pawan can finish a task in 22.5 days, and Pawan and Chirag can complete 60% of the same task in 14.4 days. Given that Amit is 12...
- There were 25 workers to complete a job in 10 days. But after 4 days, 10 workers were reassigned. How many more days will be needed now?
- A can copy 70 pages in 25 hours, A and B together can copy 135 pages in 25 hours. Then in how many hours B can copy 10 pages.
- Ram can do a piece of work in 12 days and Shyam can do the same work in 20 days. They both started work together, Ram left 4 days before the completion of ...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt