Question
P can complete a job in 30 days. Q alone can complete
the same job in 20 days. P works for 18 days and then the remaining job is completed by Q. How many days will it take for Q to complete the remaining job alone?Solution
P’s 1 day work = 1/30 P’s 18 day work = 18/30 = 3/5 days,Remaininng work = 1 - 3/5 = 2/5 Q’s 1 day work = 1/20 days, Q’s 2/5 day work = 1/20 × 5/2 = 1/8 Q will complete the remaining job alone in 8 days.
Which part of the flower is responsible for producing pollen?
Which vitamin helps in improving night vision?
In a nuclear reactor, one of the following is used as a fuel.
The force required to maintain an object at a constant velocity is
Which gas is used in the process of photosynthesis?
What is the primary source of the Sun’s energy?
Device used to convert sound into electrical signals:
A gas is compressed at constant temperature. Which of the following will decrease?
Which one of the following oxides reacts with both acid and base?
Which of the following is an example of a plant which reproduce through its buds?