Question
P can complete a job in 30 days. Q alone can complete
the same job in 20 days. P works for 18 days and then the remaining job is completed by Q. How many days will it take for Q to complete the remaining job alone?Solution
P’s 1 day work = 1/30 P’s 18 day work = 18/30 = 3/5 days,Remaininng work = 1 - 3/5 = 2/5 Q’s 1 day work = 1/20 days, Q’s 2/5 day work = 1/20 × 5/2 = 1/8 Q will complete the remaining job alone in 8 days.
Which life insurance company has launched the ‘NIFTY Smallcap Quality Index Fund’ in the ULIP segment that provides an excellent opportunity to pa...
Which ministry administers The National Fellowship Scheme [NFS]?
Who inaugurated the 'Garia and Borsho Boron Utsav' 2025 in Agartala?
According to Union Budget 2023-24, consider the following statements regarding the Marine sector:
1. Marine products recorded the highest export ...
Which National Park was recently named the second-largest butterfly diversity hub in India?
What decision did the Madhya Pradesh cabinet make regarding ministers' income tax payments?
Which organization had its FCRA licence cancelled by the Union Home Ministry due to alleged rule violations in 2024?
Which of the following portal was recently launched by Kotak Mahindra Bank to offer comprehensive digital banking and value-added services to its busine...
According to the Macquarie Dictionary, which of these words has been declared as the word of the year for 2022?
Samvardhana Motherson International (Samil) has signed an agreement to acquire Germany-based Dr Schneider Group for _______ as part of its diversificati...