Start learning 50% faster. Sign in nowP’s 1 day work = 1/30 P’s 18 day work = 18/30 = 3/5 days,Remaininng work = 1 - 3/5 = 2/5 Q’s 1 day work = 1/20 days, Q’s 2/5 day work = 1/20 × 5/2 = 1/8 Q will complete the remaining job alone in 8 days.
Recently Ministry of Ayush to organise its first ‘Chintan Shivir’ at which of the following National Park?
What significant role does the rover play in the NASA and Japan's lunar mission agreement?
Consider the following statements:
1. Hungary has taken over the rotating presidency of the EU Council for six months.
2. One of Hungary's...
Who is the chairman of the Central Board of Direct Taxes (CBDT)?
Which country has launched the first fleet of hydrogen powered passengers trains?
What was the total investment allocated for semiconductor projects approved near Noida International Airport by the UP Cabinet?
Ayushman Bharat Digital Mission was launched in which year?
Who was honored with the prestigious M.S. Swaminathan Award for his contributions as a scientist and extension specialist in agronomy?
The ‘School Chalo’ abhiyan was recently launched in?
Which of the following IIT has entered the list of top 50 institutions for engineering in the QS World University Rankings by Subject 2023?