Question
Individual βMβ can do a piece of work in 40 days,
while βMβ and βNβ together can do it in 16 days. If βNβ worked alone for 10 days and left, how many days will βMβ take to complete the remaining work?Solution
Let the total work = 80 units {L.C.M of 40 and 16}
Then, efficiency of βMβ = 80 Γ· 40 = 2 units/day
Combined efficiency of βMβ and βNβ = 80 Γ· 16 = 5 units/day
So, efficiency of βNβ = 5 β 2 = 3 units/day
So, work done by βNβ alone in 10 days = 3 Γ 10 = 30 units
Remaining work = 80 β 30 = 50 units
Time taken by 'M' alone to complete the remaining work = 50 Γ· 2 = 25 days
Which statement accurately reflects the mandatory nature of Section 3 of the Limitation Act, 1963?Β
Which case gave a narrow interpretation to Art. 21 of the Constitution?
Select the correct pairing of Section and its title as per the Code of Criminal Procedure, 1973.
In chief- examination, leading question________.
A Private Company may not issue securities
Supremacy of Law is the first meaning of Rule of Law was established by?
As per the Code on wages, 2019 the Central Government shall fix floor wage taking into account __________ of a worker in such manner as may be prescribed
A and B were married. During marriage A committed forgery and communicated it to B, his wife. After some time divorce took place between A and B, and B ...
As per section 201 of the Contract Act an agency is terminated by___________________
Which of the following cases laid down the rule of Strict-Liability?