Question
Person βRβ can complete a task in 60 days, and
together with βSβ, they can do it in 24 days. If βSβ worked alone for 18 days and then left, how many days will βRβ take to finish the remaining work?Solution
Let the total work = 120 units {L.C.M of 60 and 24}
Then, efficiency of βRβ = 120 Γ· 60 = 2 units/day
Combined efficiency of βRβ and βSβ = 120 Γ· 24 = 5 units/day
So, efficiency of βSβ = 5 β 2 = 3 units/day
So, work done by βSβ alone in 18 days = 3 Γ 18 = 54 units
Remaining work = 120 β 54 = 66 units
Time taken by 'R' alone to complete the remaining work = 66 Γ· 2 = 33 days
which state has recently announced the formation of an expert committee to examine ways for the implementation of a uniform civil code?
What is the primary goal of the India - EU initiative for EV start - ups focusing on Battery Recycling Technologies?
Exercise βVayushakti-26β was conducted by the Indian Air Force at which location?
Consider the following statements:
I. “Turn Your Body to the Sun” is an Indian documentary film.
II. The Mumbai Internationa...
- Where will the Fisheries Startup Conclave 2.0 be held on March 8, 2025?
How is India contributing to Sri Lanka's digital identity project?
Which product category saw a 60% increase in Australian exports to India after the implementation of ECTA?
Which global event did External Affairs Minister S. Jaishankar attend in Italy during his visit?
Metaβs cloud deal with Google is valued at approximately how much and over what duration?
India has the worldβs largest thorium reserves, with rich deposits located in which of the following states?