Question
Person βRβ can complete a task in 60 days, and
together with βSβ, they can do it in 24 days. If βSβ worked alone for 18 days and then left, how many days will βRβ take to finish the remaining work?Solution
Let the total work = 120 units {L.C.M of 60 and 24}
Then, efficiency of βRβ = 120 Γ· 60 = 2 units/day
Combined efficiency of βRβ and βSβ = 120 Γ· 24 = 5 units/day
So, efficiency of βSβ = 5 β 2 = 3 units/day
So, work done by βSβ alone in 18 days = 3 Γ 18 = 54 units
Remaining work = 120 β 54 = 66 units
Time taken by 'R' alone to complete the remaining work = 66 Γ· 2 = 33 days
The headquarter of International Monetary Fund (IMF) is located in __________.
What is the percentage of Scheduled Tribes in the Total Population of Uttar Pradesh?
The SIMBEX exercise of 2022 a maritime bilateral exercise between India and Singapore was held at Visakhapatnam from _____ to _____ October,2022.
Consider the following statements about Pandit Nikhil Ranjan Banerjee: Β
(I) He was an Indian classical flutist.
(II) He was associated w...
What is the key focus of the newly launched Unified Lending Interface (ULI)?
When was Wildlife Protection Act was enacted ?
According to data from the National Payments Corporation of India (NPCI), India's instant payment system Unified Payment Interface (UPI) showed a slight...
Which organization did REC Limited sign an MoU with to finance infrastructure projects?Β
Which city in Uttar Pradesh is known for its wooden handicrafts?
Which two district connected in Ganga Expressway ?