Question

Person ‘R’ can complete a task in 60 days, and together with ‘S’, they can do it in 24 days. If ‘S’ worked alone for 18 days and then left, how many days will ‘R’ take to finish the remaining work?

A 25 days
B 40 days
C 33 days
D 16 days