The amount of work completed by 24 men in 5 hours is equivalent to the work done by 21 women in 8 hours. A team of 33 men, working 6 hours daily, can finish a task in 15 days. Determine how many days it will take for 14 women, working 9 hours per day, to complete the same task.
Solution
Let the efficiency of a man be 'm' units/hour and the efficiency of a woman be 'n' units/hour Then, 24 X m X 5 = 21 X n X 8 Or, m:n = 168:120 = 7:5 So, let the efficiency of a man and of a woman be 7 units/hour and 5 units/hour, respectively. Total work required to complete the task = 33 X 7 X 6 X 15 = 20790 units So, number of days taken by 14 women working 9 days to complete the same task = 20790 ÷ (14 X 5 X 9) = 20790 ÷ 630 = 33 So, required time taken = 33 days
- 40 women working 10 hours a day take 12 days to complete a project. How many women working for 7 hours a day are needed to complete twice the given project...
- A can finish a piece of work in 12 days and B can finish it in 18 days. They work together for 4 days, after which B leaves. In how many more days will A c...
- A’ and ‘B’ together can complete a work in 20 days while ‘A’ takes 25 days to complete the same work alone. If ‘C’ is 60% more efficient than ‘B’, then fin...
- Rahul can complete a work in 12 days and Ayush in 15 days. If they work together for 3 days, then the fraction of work that will be left is:
- Asmita and Bhanu working together can complete the task in ____ days, and the efficiency of Sam is 50% more than that of Asmita. Bhanu alone can complete o...
- Shudhanshu completes 1/2 of work in 12 days, then he completes the remaining work with the help of Neeraj in 5 days. The time required for Sudhanshu and N...
- X and Y alone can complete a work in 10 and 40 days, respectively. 50% of the work is completed by Z in 20t days, and the remaining work is completed by X ...
- A and B can complete a piece of work in 12 days, B and C in 15 days and A and C in 20 days. In how many days can B alone complete the work?
- ‘A’ alone can complete a work in 40 days while ‘A’ and ‘B’ together can complete the same work in 30 days. How much per...
- ‘Pawan’, ‘Qureshi’, and ‘Ram’ can finish 50%, 1/3, and 3/4 of a job in 24, 18, and 54 days, respectively. If ‘Pawan’ and ‘Qureshi’ start the job together a...