Question
The amount of work completed by 24 men in 5 hours is
equivalent to the work done by 21 women in 8 hours. A team of 33 men, working 6 hours daily, can finish a task in 15 days. Determine how many days it will take for 14 women, working 9 hours per day, to complete the same task.Solution
Let the efficiency of a man be 'm' units/hour and the efficiency of a woman be 'n' units/hour Then, 24 X m X 5 = 21 X n X 8 Or, m:n = 168:120 = 7:5 So, let the efficiency of a man and of a woman be 7 units/hour and 5 units/hour, respectively. Total work required to complete the task = 33 X 7 X 6 X 15 = 20790 units So, number of days taken by 14 women working 9 days to complete the same task = 20790 ÷ (14 X 5 X 9) = 20790 ÷ 630 = 33 So, required time taken = 33 days
Which companies manufactured the least number of defective cars in 2017?
Study the given graph and answer the question that follows.
Revenue and Expenditure (In ₹ Crores) of a company XYZ from 2014-19
What is the difference between the sales of Nike in Chandigarh and that in Bhopal?
 In which of the following years is the profit of the Airlines the maximum?
Study the given graph and answer the question that follows.
...
If total sales of cars of all brands together increases by 10% in 2018 and the the sales of Santro in Maharshtra increased by 15% keeping percentage dis...
What is the difference between the sales of Santro in Uttrakhand and that in Haryana?( in thousand units)
The total sales of Fila, Adidas and Woodland in 2017 is approximately what percent of the total sales of Nike in all cities together in 2017?
If total sales of cars of all brands together increases by 10% in 2018 and the the sales of Santro in Maharshtra increased by 15% keeping percentage dis...
What was the respective ratio between the number of Petrol Perfect Cars manufactured by Honda Company and the number of defective Cars manufactured by M...