Question
Akash can finish a task alone in
24 days, while Akash and Bittu working together can complete the same task in 14 days. If Bittu starts the work alone and stops after 19.6 days, how many days will Akash need to finish the remaining work by himself?Solution
ATQ,
Let the total work = L.C.M of 24 and 14 = 168 units So, efficiency of ‘Akash’ alone = 168 ÷ 24 = 7 units/day Combined efficiency of ‘Akash’ and ‘B’ = 168 ÷ 14 = 12 units/day So, efficiency of ‘Bittu’ alone = 12 – 7 = 5 units/day Work completed by ‘Bittu’ alone in 19.6 days = 19.6 × 5 = 98 units Time taken by ‘Akash’ alone to complete the remaining work = (168 – 98) ÷ 7 = 10 day
Who was honored with an honorary Doctor of Science degree by IIT Kharagpur?
In October 2021, the Board of Control for Cricket in India (BCCI) unveiled Ahmedabad and _______ as the two new teams for the Indian Premier League (IPL...
Who has been elected as the caretaker Prime Minister of Pakistan?
In the financial year 2023-24, what was the percentage growth in IREDA's loan book outstanding, marking a significant increase in its financial performa...
Which sectors are expected to see higher loan demand in 2025–26, as per RBI’s survey?
Which mutual fund house has renamed US Debt ETF Fund As US Treasury Bond 0-1 Year Fund Of Fund?Â
Who won the IAA Golden Compass Award at the 45th IAA World Congress?
Who will chair the third Global South Summit in August 2024?
Concerning Srinagar's designation as a World Craft City:
1. The designation was given by the World Crafts Council (WCC).
2. It recognizes ...
Recently Which of the following food delivery apps has agreed to buy restaurant technology and dining out platform “ Dineout ”?