      Question

      Working alone, 'C' can complete a job in 30 days. 'D'

      takes 20% less time than 'C' to finish the same job. Calculate the percentage of work done by 'C' and 'D' together in 4 days.
      A 35% Correct Answer Incorrect Answer
      B 30% Correct Answer Incorrect Answer
      C 45% Correct Answer Incorrect Answer
      D 55% Correct Answer Incorrect Answer

      Solution

      ATQ, Time taken by 'D' alone:ย  0.8ร—30=24 days Total work: LCM of 24 and 30 = 120 units Efficiency of 'C': 120/30=4 units/day Efficiency of 'D': 120/24=5 units/day Combined efficiency of 'C' and 'D': 4+5=9 units/day Work done in 4 days: 9ร—4=36 units Percentage of total work done: (36/120)ร—100=30 Therefore, 'C' and 'D' together complete 30% of the work in 4 days.