Question
'A' and 'B' can do a piece of work together in 30 days.
They worked together for 18 days, and then left the work. The remaining job was finished by 'C' alone in 12 days. How many days would 'C' alone take to finish 72% of the whole work?Solution
ATQ,
Fraction of work done by 'A' and 'B' = 18 / 30 = 3/5 Fraction of work done by 'C' = 1 - 3/5 = 2/5 So, number of days taken by 'C' alone to complete the entire work = 12 ÷ (2/5) = 30 days So, time taken by 'C' to complete 72% of the work = 30 × 0.72 = 21.6 days
Which of the following is an Expense for an accounting year
Which segment of the debt markets has highest market capitalization?
Arrange the following ratios in the order in which they appear on a common-size income statement, from top to bottom:
(A) Gross profit margin
...For a non-financial firm, are depreciation expenses and interest expenses included or not included from operating expenses in the income statement?
Identify the incorrect statement about NBFC (Nonbanking finance company)
If income increase, the investment will ______
Which account in the BOP includes transactions related to currently produced goods and services?
What is the primary purpose of the Balance of Payments (BOP)?
What would be the amount of profits?
In the finance industry, which application of data analysis is most critical for reducing credit risk?