Question
'A' and 'B' can do a piece of work together in 30 days. They worked together for 18 days, and then left the work. The remaining job was finished by 'C' alone in 12 days. How many days would 'C' alone take to finish 72% of the whole work?
More Time and work Questions
- 18 women can do piece of work in 12 days. 12 men can do the same piece of work in 9 days. Find in how many days will 8 men and 8 women complete that work?
- 'A', 'B' and 'C', alone can do some work in 16 days, 24 days and 48 days, respectively. If they work together for wages of Rs. 7,800, then find the differe...
- 18 workers can complete 9 tasks in 24 hours. Find the time required by 12 workers to finish 15 tasks.
- A can finish a piece of work in 10 days and B can finish the same work in 15 days. If they work together, in how many days will the work be completed?
- ‘A’ and ‘B’ can do a piece of work in 20 days and 30 days, respectively. If they started the work together and worked on it for 7 days, then find the time ...
- Suppose Y individuals can complete a task in (Y - 28) days, and (Y + 12) individuals can finish the same task in (Y - 32) days, what is the number of days ...
- Rahul alone can do 60% of the same piece of work in (z-4) days. Queen and Rahul together can do 75% of the same piece of work in (0.5z+4) days. Pankaj alon...
- The time taken by ‘A’ to build a wall alone is 40% more than the time taken by him to build it along with ‘B’. ‘B’ will take how much percent more time to ...
- A 250 litres mixture contains only water and phenyl in the ratio 3:2, respectively. If 60 litres of this mixture is replaced with 90 litres of alcohol, the...
- A group of workers was put on a job. From the second day onwards, 1 worker left work everyday. If no worker was left when 52% of the work gets completed, f...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)