Question
Workers A and B can finish a task in 30 days when
working together. They worked for 18 days, and then C completed the rest of the task alone in 12 days. How many days will C alone take to finish 75% of the work?Solution
ATQ,
Fraction of work done by A and B = 18 / 30 = 3/5
Fraction of work done by C = 1 - 3/5 = 2/5
So, number of days taken by C alone to complete the entire work = 12 ÷ (2/5) = 30 days
So, time taken by C to complete 75% of the work = 30 × 0.75 = 22.5 days
National Technology Day is observed every year to commemorate:
At the 66th National Film Awards, 2019, which state wins the Most Film Friendly State?
Which of the following statements related to the launch of Platform of Platforms (POP) are correct?
1) The Union Minister of Agriculture and Farm...
………………………….won India's first-ever silver in women's weightlifting (49 kg), becoming the first Indian Olympic medallist in the sport ...
The per hectare seed rate of tobacco is:
The state of Uttar Pradesh ranks _________ for availing benefits under the Pradhan Mantri Kisan Samman Nidhi Yojana (PM Kissan).
Mahindra and Mahindra Financial Services Ltd announced a strategic partnership with which Payments Bank to enhance credit access to a larger customer b...
The Xinjiang region, which was seen in the news due to the collapse of a global mine, is located in which country?
Which of the following games is used to train the inner travelers?
Which of the following Articles of the Constitution of India is related to the promotion of co-operative societies?