Question
Workers A and B can finish a task in 30 days when
working together. They worked for 18 days, and then C completed the rest of the task alone in 12 days. How many days will C alone take to finish 75% of the work?Solution
ATQ,
Fraction of work done by A and B = 18 / 30 = 3/5
Fraction of work done by C = 1 - 3/5 = 2/5
So, number of days taken by C alone to complete the entire work = 12 ÷ (2/5) = 30 days
So, time taken by C to complete 75% of the work = 30 × 0.75 = 22.5 days
If there exists a specific sports fund, the expenses incurred in relation to sports activities will be taken to:
On what basis is vertical analysis made?
Which category of banks has the highest Priority Sector Lending (PSL) target as a percentage of Adjusted Net Bank Credit (ANBC)?
In an Enterprise Information System, the primary function of a Financial and Accounting System is to:
a) Manage human resources' activities
<...Which of the following documents is NOT accepted as valid proof for opening a current account by a sole proprietor?
What is the main purpose of variance analysis in budgeting in cost accounting?
What duties are taxes on intra-State supplies?
Application Controls deal with controls related to:Â
The 'Stores Ledger' in material accounting is maintained based on the principle of:
Aqua Ltd. just declared the earnings of Rs. 23 per share. The company is involved in the manufacture of cars. The average PE of electronics industry is ...