Question
Workers A and B can finish a task in 30 days when
working together. They worked for 18 days, and then C completed the rest of the task alone in 12 days. How many days will C alone take to finish 75% of the work?Solution
ATQ,
Fraction of work done by A and B = 18 / 30 = 3/5
Fraction of work done by C = 1 - 3/5 = 2/5
So, number of days taken by C alone to complete the entire work = 12 ÷ (2/5) = 30 days
So, time taken by C to complete 75% of the work = 30 × 0.75 = 22.5 days
The depreciation of assets is computed on their:
On what basis is vertical analysis made?
In the case of Maruti-Suzuki, the Union Government surrendered partial ownership and sold the majority stake to Suzuki of Japan in the course of time. T...
When a publicly listed company buys back its own shares from the market, it is known as:
For a large infrastructure project, which of the following is typically the MOST expensive source of finance?
Which of the following is true regarding e-invoicing under GST?
A company manufactures two products, A and B. The contribution per unit for A is ₹50 and for B is ₹60. Each unit of A requires 4 machine hours, and ...
A company has the following data for two products: Product A requires 200 machine hours and 50 setups; Product B requires 400 machine hours and 10 setup...
Parent Ltd. acquired 80% of Subsidiary Ltd. on 1st April 2023. At the time of acquisition, the subsidiary’s retained earnings were Rs. 5,00,000. On 31...
In the context of MSMEs, what does SMAS stand for?